《风口风量测试调整记录doc.doc》由会员分享,可在线阅读,更多相关《风口风量测试调整记录doc.doc(1页珍藏版)》请在三一办公上搜索。
1、风口风量测试调整记录GD2302050单位(子单位)工程名称怡新花园A4-A6、A9-A10栋子分部(系统)工程名称防排烟系统工程安装单位汕头市建安(集团)公司项目经理(负责人)施工执行标准名称及编号通风与空调施工质量验收规范 GB50243-2002系统名称防排烟系统测试日期风口位置与编号风口形式及规格(mm)风口有效面积(m2)实测风速(m/s)实测风量(m3/h)设计风量(m3/h)测试值与设计值偏差(%)12345平均地下室负二层P(Y)-125006001.510.710.810.210.510.810.638190397864.0%地下室负二层S-120004000.85.785.
2、735.775.785.745.7620740216084.0%地下室负二层S-220004000.85.685.685.735.705.715.7020520216085.0%地下室负二层P(Y)-225006001.510.810.310.510.610.310.537798397865.0%地下室负二层P-14804100.22.242.252.262.282.222.25809082552.0%地下室负二层P(Y)-325006001.510.610.810.510.510.610.638010397864.4%地下室负二层S-320005001.05.765.715.725.755.
3、715.7320635216084.5%地下室负一层S-325006001.511.011.511.311.611.111.340745424454.0%地下室负一层S-325005001.258.178.158.218.148.188.1729422300232.0%天面层JS-125006001.57.447.407.417.407.457.4226730281355.0%天面层JS-225006001.57.477.527.507.537.487.5027010281354.0%天面层JS-325006001.57.457.487.467.467.457.4626869281354.5%天面层JS-425006001.57.757.687.647.717.727.7027729287353.5%天面层JS-525006001.57.687.717.657.677.737.6927672287353.7%安装单位检查评定结果专业工长(施工员)测试人员符合规范和设计要求项目专业质量检查员: 年 月 日监理(建设)单位验收结论专业监理工程师(建设单位项目专业技术负责人): 年 月 日