《hc杭长高速某预应力变截面连续箱梁挂蓝施工方案secret.doc》由会员分享,可在线阅读,更多相关《hc杭长高速某预应力变截面连续箱梁挂蓝施工方案secret.doc(47页珍藏版)》请在三一办公上搜索。
1、yuan, an increase of 17.5%; local government general budget revenue of 500 million Yuan, . Painting, model culture creates new Ma Church community, creating Lake scenic spot culture education base, received high evaluation from provincial and municipal discipline Inspection Commission, the peoples d
2、aily special report. Constantly promote independent Commission against corruption culture construction to rural extends, created established Dahlin rural industry Park independent Commission against corruption culture positions, formed has a support service low double excellent of members lead team,
3、 constantly perfect and established Park funds assets management, and village audit supervision, and villagers democratic financial, system, strengthening Park party, and Chief, and financial, full public, powerful to guarantees has new rural construction, by city rural style clean government inspec
4、tion unit led of height evaluation. Through the implementation of honest and clean government cultural construction, and effectively educate the broad masses of party members and cadres and consciously regulated behavior and discipline, honesty in politics and culture to create a good atmosphere and
5、 fresh development environment. Although we in implement implementation independent Commission against corruption guidelines aspects made has must effectiveness, but away from superior of requirements also exists must of distance, main performance for: a is system enough sound, education, and superv
6、ision, and prevention, and punishment, aspects long-term mechanism also enough perfect, especially in enrollment bid work regulatory aspects also needed strengthening; II is regulatory supervision exists lost of Yu wide, and lost of Yu soft, investigation illegal disciplinary case of efforts also ne
7、eded strengthening, individual sector and cadres also different degree exists treat gift, not to benefits not do, and mess do of phenomenon; Three for honest work is the new situations and new problems in finding timely enough, treatment measures are not strong enough. To solve these problems, we wi
8、ll proceed from the following five aspects of rectification, make sure to implement the provisions of the code. (A) deepening the learning, enhance the consciousness of honesty in politics. To create event as an opportunity to Excel and learning party, further increasing the governance capability an
9、d advanced construction, reinforced rules of the broad masses of party members and cadres awareness, sense of responsibility, sense of honor, improve working ability and level of scientific development. Should make full use of meetings, in particular central group learning opportunity, further stren
10、gthening the study and education of the code, the intensive warning education, education the majority of party members and cadres known fear, knew fear, honesty in politics of tension the strings, consciousness and enhancing the implementation of the initiative. Also, pay attention to apply what the
11、y have learned, consciously study results into planning work, new ideas,XX工程集团有限公司目录XX大桥主梁施工方案1一、工程概况1二、编制依据1三、总体施工思路11.主要施工步骤12.主要施工工艺流程图21.10号块施工工艺流程图21.21-10号块施工工艺流程图21.3边跨现浇段施工工艺流程图31.4合拢段施工工艺流程图4四、分项工程施工方法41.0号块现浇施工41.10号块支架搭设41.20号块梁体施工61.3临时固结体系施工62.挂蓝悬浇施工62.1挂蓝拼装62.2静载实验72.3挂蓝行走72.4挂蓝施工注意事项7
12、2.5节段悬浇施工83.边跨现浇段施工83.1现浇支架搭设83.2 现浇段梁体施工104.合拢段施工104.1 合拢施工准备104.2 边跨合拢施工114.3 中跨合拢施工12五、关键工序施工141.模板工程141.1模板安装141.2模板安装注意事项142.钢筋工程152.1钢筋检验152.2钢筋制作、安装152.3钢筋施工注意事项163.梁体砼浇筑163.1浇筑前准备工作163.2浇筑砼过程163.3砼浇注注意事项174.预应力施工174.1预应力体系施工工艺流程图174.2预应力波纹管安装184.3预应力钢绞线制作和安装184.4施加预应力184.5孔道压浆194.6梁体封锚204.7预
13、应力施工注意事项205.模板、现浇支架拆除21六、主梁施工质量控制22七、施工控制231.施工控制内容232.施工控制方案242.1 控制原则242.2施工控制方法252.3线形控制中的注意事项29八、质量保证体系301.质量目标及职责301.1 项目经理301.2项目总工311.3专职质检工程师311.4质检工程师321.5专业工程师331.6设备工程师331.7施工班组长331.8工班质检员342.质量保证体系框图343.质量保证措施363.1 组织、制度保证措施36九、安全保证体系371.安全目标372.安全保证体系框图383.安全保证措施393.1组织制度措施393.2安全保障措施39
14、十、材料设备计划表421.主要设备表42new measures to promote work, the courage to take responsibility, dare to break hard to ensure district, Government decisions and arrangements to implement. (B) strengthening supervision, severely punish acts of violation. One is to open the channels of supervision. Vigorously pr
15、omote the party affairs public, open, widely accepted supervision by the masses, pay attention to social groups and public opinion supervision, the powerful force formed to urge party members and leading cadres properly exercise their powers. Second, strong supervision and inspection. Democratic lif
16、e into full play, important briefings, reports related to personal matters and evaluation of cadres study of inner-party supervisory system, a comprehensive grasp of guidelines for the implementation of the independent Commission against corruption-related cases of leading cadres of party members, f
17、ocus on strengthening key areas of project selection, funding, officials monitor, detect and rectify the problem, promote honesty in politics. Third, strengthen disciplinary investigation. Seriously the implementation of JI .Recently, the County leading bodies at the county level to carry out three
18、trees practice, which is to improve the governing ability and promoting the development of XX effective measure. I carefully follow your deployment requirements, and actively participate in the three trees campaign. Read Group, prepared by the Department in the near future of the ideological and pol
19、itical construction of leading cadres in the city reader, read the relevant information, larger harvest, inspired. I think the ability of repelling is to strengthen the partys governing capacity in questions of the construction of meaning, an important topic remains in front of party members and cad
20、res at all levels, we need to further explore and ponder. The ability of repelling the name suggests, is asking party members and cadres at all levels in particular, leading cadres at all levels, not only ourselves, establish a correct concept of the independent Commission against corruption, politi
21、cal integrity, self-discipline, rejection of corruption, made for the people, pragmatic, honest leadership, and strengthen the sense of responsibility, earnestly implement the responsibility of uncorrupted, implementation of the baolian anti-corruption measures to ensure the realization of business-
22、building, construction of a win-win situation. Next, I combined with their thinking, experience and contact XX practical, on how to enhance the ability of repelling, on four aspects of cognition. Irregularities, please comment. First, the construction of the propulsion system, and enhance the system
23、 of corruption since the founding of our party, have been thinking about tackling corruption. Currently, democratic legal system, management system and supervision mechanism is not perfect, administrative acts are not very standardized, Enterprise behavior and market behavior, corruption presents a
24、diverse, pluralistic, complex trends, this shift the struggle between the two, will accompany43XX大桥主梁施工方案一、 工程概况杭长高速第XX合同段起点桩号为K9+888,终点桩号为K14+040,其中XX大桥起点桩号为K10+498,终点桩号为K10+700,全长202米,结构形式为55+92+55米现浇预应力连续钢构单箱单室箱梁。本桥主墩下部结构采用6根直径1.5米的钻孔灌注桩,长方形承台,实体墩身。本桥上部结构为55+92+55米三跨预应力变截面连续箱梁,箱梁顶板宽度13.25米,厚0.28米
25、,设2%横坡;底板宽7.75米,厚度由0.25米从跨中至距主墩中心3.5米范围按二次抛物线变化成0.767米,横桥向底板与顶板平行;0#块箱梁两高5.5米,跨中梁高2.8米,箱梁梁高从距跨中至距主墩中心1.5米处按二次抛物线变化。腹板厚度1-5号块件为0.75米,8-12号块件为0.55米,在6-7号块件范围内由0.75米按直线到0.55米;翼缘板悬臂长度为2.75米,端部厚0.25米,根部厚0.65米。二、 编制依据1)杭长高速第XX合同段施工图设计2)公路桥涵施工技术规范实施手册3)路桥施工计算手册4)钢结构设计手册三、 总体施工思路1. 主要施工步骤1)0#块施工2)拼装悬浇挂蓝及模板系
26、统、预压、验收、就位。3)施工后续梁段4)施工边跨现浇段5)合拢段施工2. 主要施工工艺流程图1.1 0号块施工工艺流程图0#块支架材料准备支架静载实验。测量弹性变形值底模标高测量浇注0#块混凝土,养护同条件养护张拉设置墩身临时固结预埋件搭设0#块现浇支架、安装底侧模安装临时固结支撑绑扎底板、腹板横隔板钢筋;安装三向预应力安装内模及端头模板绑扎顶板钢筋;安装顶板预应力;预埋挂蓝锚固孔道取砼试件75%设计强度压浆、封锚1.2 1-10号块施工工艺流程图绑扎块件底板、腹板钢筋;安装预应力挂蓝拼装同条件养护张拉取砼试件压浆、封锚浇注块件混凝土,养护安装1#块底侧模板挂蓝静载实验、测量弹性变形值校正模
27、板平面位置、标高安安装底侧模板安装内模及端头模板绑扎顶板钢筋;安装顶板预应力;预埋挂蓝锚固孔道75%设计强度脱模、挂蓝前移 1.3 边跨现浇段施工工艺流程图支架材料准备支架基础处理支架搭设安装底侧模板支架预压、静载实验、测量弹性变形值支座安装绑扎底板、腹板钢筋,安装预应力同条件养护取砼试件浇注混凝土,养护安装内模及端头模板绑扎顶板钢筋;安装顶板预应力准备施工合拢段1.4 合拢段施工工艺流程图合拢吊架安装安装底、侧模板测量两端高差并监测其温度影响合拢段水箱配重吊架预压、测量其弹性变形值安装劲形骨架,锁扣合拢段绑扎底板、腹板钢筋,安装预应力原材料检查安装内模及端头模板配合比审查绑扎顶板钢筋,安装预
28、应力拌制砼、输送同条件养护张拉取砼试件75%设计强度压浆、封锚选择合拢温度时浇注混凝土四、 分项工程施工方法1. 0号块现浇施工1.1 0号块支架搭设1.1.1 支架设计结合本桥主墩承台及临时固结体系图纸,本桥0号块支架体系直接在承台上方利用钢管立柱与贝雷梁、型钢相结合的方式进行搭设。1.1.2 支架搭设该支架在本桥临时固结已用8根钢管立柱的基础上,外加6根钢管立柱,形成支架主要承重支撑。在墩身上适当高度处预埋安装贝雷梁用的临时钢板(制作成贝雷梁阴头的形式)。将6组贝雷梁安装于钢管立柱之上(每两排为一组),形成支架中间承重结构,然后在贝雷梁上方先横桥向安装25H型钢,最后再纵桥向安装25b工字
29、钢,作为底模支撑。为确保钢管立柱的稳定性,在适当位置两钢管立柱之间可增加剪刀型斜撑。1.1.3 支架预压待支架搭设完成后,安装好底、侧模板,然后对支架进行预压,支架预压采用在承台上预埋钢绞线反拉进行,以消除支架非弹性变形,同时经过观测,以计算出支架在外荷载作用下的弹性变形值。支架预压荷载重量为新浇混凝土自重、钢筋自重和施工人员及设备荷载总和的120。支架预压过程如下: 在安装好钢绞线、锚具、夹片及千斤顶和油泵以后,开始用张拉预应力的方式对支架进行预压,布设标高控制点,初测支架标高。 张拉30%con,测量支架沉降量。 张拉60%con,测量支架沉降量。 张拉100%con,测量支架沉降量。 张
30、拉120%con,测量支架沉降量。 对预应力钢绞线卸载至0,测量支架回弹量。 测量数据整理。1.2 0号块梁体施工待支架预压及验收完成后,开始绑扎0号块底板、腹板、横隔梁钢筋,同时安装预应力波纹管,经检查验收合格后,再安装内模、横隔梁模板、端头模板及顶板钢筋和预应力,验收合格后方可进行混凝土浇筑。结合0号块结构形式,本桥0号块混凝土浇筑可一次性浇筑完成,采用罐车运输至指定地点,泵车浇筑的方式进行。浇筑顺序为底板两侧腹板、横隔梁顶板。1.3 临时固结体系施工桥临时固结体系采用设计图纸中的建议,主要承重结构为8根60820钢管,该钢管由承台向上直至0#节段箱梁底。在每根钢管中心位置处(承台以下1.
31、5米)预埋4根钢绞线,临时固结时每根钢绞线张拉15吨的力。详见XX大桥临时固结图。由于在0#块张拉完成后,拆除临时支架,将钢管桩接长至梁底,然后张拉临时固结钢绞线。(张拉时0#块横隔板两侧对应钢束必须同时张拉)2. 挂蓝悬浇施工2.1 挂蓝拼装挂篮组件在工厂内制作好以后运至现场拼装,采用塔吊和吊机辅助。0#块已经施工完成,在其顶面形成的平台上即可拼装挂篮。本桥挂蓝采用三角桁架式挂蓝,拼装时先在0号块上拼装主桁架和锚固系统,然后再拼装底篮系统和行走系统。2.2 静载实验为保证挂篮结构的可靠性,清除非弹性变形,量测弹性变形量,确保箱梁施工的安全和质量,在第一次使用之前必须对挂篮进行试压。对已拼装的
32、挂篮按设计荷载加安全系数进行试压,以求得挂篮在不同长度(3.75m、4m、4.5m)时不同荷载下的变形挠度值。拟采用水箱压重法进行实验2.3 挂蓝行走本桥施工使用挂蓝行走采用行走反滚轮配合前支点滑行方式进行。挂蓝行走步骤如下:张拉封锚完成后脱模固定行走轨道松开后锚精轧螺纹使行走反滚轮作用于行走轨道之上千斤顶上顶前支座,在前支座下方,轨道上方安放行走圆钢安装行走葫芦拉动葫芦挂蓝前移适当距离测量放样校正挂蓝平面位置。2.4 挂蓝施工注意事项为防止挂蓝构件脱落及挂蓝的走行过程中的错误操作,导致灾难性后果,重点监控的项目如下: 本工程挂篮后锚固采用预埋孔道穿精扎螺纹钢筋锚固,混凝土荷载通过三角桁架对后
33、锚产生上拔力,施工时后锚锚固螺栓和后锚分配了必须严格检查质量,防止挂蓝发生倾覆。 挂蓝在后锚松开之前,必须将行走轨道与主梁竖向预应力筋紧固好,同时检查该处精轧螺纹钢筋接头,防止挂蓝倾覆。 挂蓝行走时单侧两个主桁架之间行走距离应相等,防止主桁架之间联系桁架应力过大发生破坏,影响挂蓝稳定性。 主梁上方两端挂蓝行走必须同步进行,防止主梁端头荷载步平衡破坏根部截面。 挂蓝到位以后,需严格校正其平面位置和底模标高,确保梁体合拢前线形顺直,标高相符。 浇注梁段混凝土时,必须由梁段中间向两边同时进行,防止挂蓝发生过大偏载。 挂蓝施工过程中,对每道工序完成后必须经过专职管理人员检查后方可进入下一道工序施工。2
34、.5 节段悬浇施工主梁节段长度有3.75米、4米、4.5米三种,每个节段预计施工周期为8-10天。节段最大重量为1号块,重156吨。所有节段钢筋绑扎、模板安装均与0号块施工顺序相同。混凝土浇筑均一次性浇筑成型。主梁节段施工时,施工用的小型器具、垃圾、废钢筋头、废钢板等均不得抛入XX河中。3. 边跨现浇段施工3.1 现浇支架搭设3.1.1 支架基础本桥支架基础带为软土地基,地质条件差。为了保证箱梁浇筑质量,在梁体投影范围内的基础先用夯机打夯密实、平整,然后再在上面浇筑25cm厚的C20砼,并且在场地周围修建排水沟,使支架基础不被水浸泡,影响基础承载力。3.1.2 支架搭设在支架基础施工完成后,对
35、箱梁支架进行放样,确定其平面位置。本桥现浇段支架采用门式脚手架搭设,门式脚手架设置上下托座,增加受力面传递。下托座底设置枕木作为底座,底座上布置门式脚手架。门式脚手架下端采用可调底座,上端采用可调托座和增加调节杆,以便调节支架的局部高度。上托座上顺桥向放置1220方木,其上横桥向放置1520方木(间距为50cm),该方木上面铺设箱梁模板。支架搭设时在即将达到设计高程时进行超平、放样,以减少模板铺设后的高度调节工作。为了增强支架的整体性,竖向每3层高度用钢管与门式脚手架连成一组48x3.5mm的水平杆,水平杆间加45斜撑钢管(横桥向和顺桥向方向同样布置)。水平杆、斜撑与门架立柱用“十字卡”卡牢。
36、架与架之间用交叉拉杆成对角连接。3.1.3 支架预压支架在初次受到荷载作用时,会发生相应的非弹性变形和弹性变形,为保证上部构造在支架拆除后能达到设计要求的外形,在支架搭设好后,对支架进行预压,以消除其非弹性变形,同时,通过测量观察以确定支架实际荷载作用下的饶度,从而为施工总梁体预拱度的设置提供实测数据。预压荷载按新浇混凝土自重、钢筋自重和施工人员及设备荷载总和的120考虑,具体施工时用与上述荷载相当的水箱进行预压。3.2 现浇段梁体施工待箱梁现浇支架搭设完毕后,开始安装箱梁模板。所有模板用竹胶板加方木组合而成。模板安装时先安装箱梁底模,然后安装侧模、内模。箱梁外侧模安装完成后即绑扎底板和腹板钢
37、筋,穿底板和腹板预应力钢束,待箱梁内模安装完成后再绑扎顶板钢筋,穿顶板预应力钢束。模板、钢筋、预应力施工必须严格按照施工规范和设计图纸进行。该边跨混凝土浇注采用一次性浇注成型的方式进行。待以上工序完成并通过检查后,即进行箱梁混凝土的浇注。混凝土浇注前应做好相关天气预报,选择好适当时间浇注,以保证浇注质量。4. 合拢段施工箱梁合拢即体系转换,是控制全桥受力状态和线型的关键工序,因此合拢顺序和工艺必须严格控制。全桥分两个合拢阶段,第一个合拢阶段合拢两边跨,第二个合拢阶段合拢中跨。合拢段混凝土均采用微膨胀砼施工。4.1 合拢施工准备、清除桥面多余的施工设备和杂物,使桥梁处于设计和标准施工荷载状态;、
38、检查合拢段处劲性骨架的预埋件,锁定型钢及焊机的准备;、压载水箱砌筑、注水及放水设备、水量监测设备的安装;、挂篮锚固孔设置及部分构件修整切除;、预应力锚齿及管道的清理、施工预应力束的穿束安装、张拉设备准备;、测量标识的预埋、清理,测量工具的准备,测量记录表编制; 、各道工序施工时间的计划安排,施工时机的选定,施工人员组织。4.2 边跨合拢施工在边跨两悬臂端安装吊架,并在悬臂端设水箱作平衡重,合拢段两侧水箱容水重量相当于合拢段所浇砼重量。吊架布置如下:将挂篮底篮纵梁前移2.5米,取出挂篮底篮后横梁,将其移至边跨悬臂端用做吊架下横梁。如图示。在设计合拢温度下,焊好合拢骨架,绑扎合拢段钢筋。浇筑合拢段
39、砼,边浇筑边同步放水。待混凝土强度达到设计强度的90%以上时按顺序张拉纵向底板束和横、竖向预应力。4.3 中跨合拢施工中跨合拢时间至少晚于边跨合拢时间十五天方可进行。在合拢段施工前,先拆除T构施工挂篮,在“T”构悬臂端和现浇端部设水箱作平衡重,合拢段两侧水箱重量相当于合拢段所浇砼重量。如图示。在设计合拢温度下,焊好合拢骨架,绑扎合拢段钢筋。浇筑合拢段砼,边浇筑边同步放水。合拢前现场锁定支座,待合拢施工完成后再解除锁定。合拢时的气温须经观测计算确定,根据测量结果计算调整高程及平面位置,在箱梁底板及顶板安装水平刚性支撑,联结前注意复查、调查两悬臂端合拢施工荷载,使其对称相等,如不相等时,应用压重调
40、整。检查梁内预应力钢束是否张拉完成。复测、调整中跨、边跨悬臂的挠度及两端的高差。合拢段的混凝土强度可提高一级,合拢段施工时气温选择在设计要求的温度进行,并宜在一天中最低气温时完成。且浇注速度要快,时间要短,并加早强剂,加强混凝土养护,悬臂端应覆盖,防止日晒。待混凝土强度达到设计张拉强度后,按设计文件要求尽早张拉预应力钢束。五、 关键工序施工1. 模板工程1.1 模板安装箱梁0号块模板采用标准钢模板和组合钢模板制作,其他节段采用与挂蓝配套的组合钢模板制作,所有端头模板用木模板制作。 箱梁底、外侧模安装0号块底模安装时,在工字钢上铺设标准钢模板。铺设前应进行测量放样,以确定模板中线位置。呆支架预压
41、完成后,应测量其标高。箱梁一般节段底模安装时,直接提升挂蓝底篮前后横梁至设计标高即可。在安装好底模后即安装腹板外侧模,外侧模安装必须竖直且 内模安装安装好箱梁整体外模后应重新进行测量放样确定梁体中线位置,待底板钢筋和腹板钢筋绑扎完成后再安装箱梁内侧模板,内侧模板采用组合钢模板,用与挂蓝配套的内模支撑架作内支撑加固。内外侧模板采用20圆钢作对拉杆。1.2 模板安装注意事项 选用模板必须有足够的强度和刚度,模板表面必须清除干净,不得粘有干硬水泥砂浆等杂物,脱模剂必须涂刷均匀,不得漏刷,以防拆模时砼表面被粘损,出现麻面。 位于梁端、横梁位置、预应力锚头位置的模板采用木模板,应按设计要求做成规定的角度
42、与形状,并保证锚头位置混凝土面与该处钢绞线的切线垂直。 所有排气孔、压浆孔、泄水孔、挂蓝锚固体系预留孔的预埋管及桥面泄水管按设计图纸固定到位,预埋件的预埋无遗漏且安装牢固,位置准确。2. 钢筋工程2.1 钢筋检验钢筋必须按不同种类、等级、牌号、规格及生产厂家分批验收、分别堆放,不得混杂,且应立标牌以示识别。钢筋在运输、储存过程中,应避免锈蚀和污染,并堆置在钢筋棚内。在钢筋进场后,要求提供附有生产厂家对该批钢筋生产的合格证书,标示批号和出厂检验的有关力学性能试验资料。进场的每一批钢筋,均进行取样试验,试验不合格的不得使用于本工程。2.2 钢筋制作、安装 钢筋制作必须按图纸设计的规格数量加以分类制
43、作,钢筋制作好后派专人检查其制作质量,合格后方可运至施工现场。钢筋的焊接绑扎必须严格按设计要求和规范施工,保证钢筋的位置正确、间距、搭接长度、焊接长度等满足规范要求。 纵向通长钢筋采用螺纹连接,接头交错排列,受拉区同一接头范围内接头钢筋的面积不得超过该截面钢筋总面积的50%。钢筋安装顺序为先绑扎底板钢筋,待安装好腹板外模和翼板底模后,再绑扎腹板钢筋,最后绑扎顶板及翼板钢筋。 为保证钢筋保护层的厚度,在钢筋与模板间设置塑料垫块,垫块与钢筋扎牢,并呈梅花状布置。2.3 钢筋施工注意事项 所有钢筋的加工、安装和质量验收均应严格按照公路桥涵施工技术规范(JTJ041-2000)的有关规定进行。 当钢筋
44、和预应力管道在空间发生干扰时,可适当移动普通钢筋位置,以保证预应力钢束管道位置准确。 钢束锚固处的普通钢筋如影响预应力施工时,可适当弯折,但当预应力施工完后应及时恢复原位。 如因浇注或振捣混凝土的需要,可对钢筋间距作适当的调整。 钢筋的下料长度应根据设计图纸尺寸准确确定。 如果分布筋与锚下螺旋筋相扰时,可适当移动分布筋或调整分布筋间距。3. 梁体砼浇筑3.1 浇筑前准备工作在模板、钢筋、预应力管道等安装完成后,应对所有预埋件、预留施工孔道进行检查,然后将模板、钢筋等用水进行冲洗干净,经检查合格后,即可浇注混凝土。3.2 浇筑砼过程本箱梁段施工采用单节段两端同时一次性浇筑成形的方式进行,浇筑混凝
45、土顺序为先浇筑底板,然后浇筑腹板,最后浇筑顶板混凝土。浇筑腹板混凝土分层浇筑的方式进行。3.3 砼浇注注意事项由于梁体浇筑混凝土时间较长,在浇筑前必须做好防雨措施,同时还必须根据雨后混凝土含水率的增加控制好混凝土的坍落度。具体应注意以下事项: 砂石料场的排水设施应准备齐全。 浇筑仓面应有足够的防雨设备。 运输工具应有足够的防雨和防滑设施。 实验室人员应注意控制好混凝土的坍落度。 新浇混凝土应及时振捣,振捣人员必须是专业的熟练工,在箱梁各转角地带和预应力钢束锚下部分应注意加强振捣,必须保证混凝土振捣密实。 混凝土浇筑完成后,应及时养护、收面,保证好梁体表面外观质量。 应注意天气情况,合理根据气象
46、状况安排施工。4. 预应力施工4.1 预应力体系施工工艺流程图安装波纹管钢绞线下料穿钢绞线制作砼试块浇注混凝土75%设计强度同条件养护张拉孔道压浆、封锚4.2 预应力波纹管安装预应力管道采用塑料波纹管。预应力钢绞线管道按照坐标位置放样,并用“井”字箍将管道定位加固。加固距离为:直线段1.0m,曲线段0.5m。管道接头处应用胶带缠裹紧密。管道定位完毕后进行预应力钢筋的穿束工作,钢束前端须用胶带紧密缠裹,以确保穿束过程中不损伤波纹管。4.3 预应力钢绞线制作和安装钢绞线下料长度时应考虑张拉端的工作长度,下料时,切割口的两侧各5cm先用铁丝绑扎,然后用切割机切割。然后在地坪上进行编束,每束内各根钢绞线应编号并顺序摆放。在波纹管、锚垫板安装完成和钢绞线编束后,即可进行钢绞线穿束工作。4.4 施加预应力4.4.1 施工准备 标定张拉设备