《hz东风隧道4 横洞反坡排水爆破通风施工方案.doc》由会员分享,可在线阅读,更多相关《hz东风隧道4 横洞反坡排水爆破通风施工方案.doc(21页珍藏版)》请在三一办公上搜索。
1、yuan, an increase of 17.5%; local government general budget revenue of 500 million Yuan, . Painting, model culture creates new Ma Church community, creating Lake scenic spot culture education base, received high evaluation from provincial and municipal discipline Inspection Commission, the peoples d
2、aily special report. Constantly promote independent Commission against corruption culture construction to rural extends, created established Dahlin rural industry Park independent Commission against corruption culture positions, formed has a support service low double excellent of members lead team,
3、 constantly perfect and established Park funds assets management, and village audit supervision, and villagers democratic financial, system, strengthening Park party, and Chief, and financial, full public, powerful to guarantees has new rural construction, by city rural style clean government inspec
4、tion unit led of height evaluation. Through the implementation of honest and clean government cultural construction, and effectively educate the broad masses of party members and cadres and consciously regulated behavior and discipline, honesty in politics and culture to create a good atmosphere and
5、 fresh development environment. Although we in implement implementation independent Commission against corruption guidelines aspects made has must effectiveness, but away from superior of requirements also exists must of distance, main performance for: a is system enough sound, education, and superv
6、ision, and prevention, and punishment, aspects long-term mechanism also enough perfect, especially in enrollment bid work regulatory aspects also needed strengthening; II is regulatory supervision exists lost of Yu wide, and lost of Yu soft, investigation illegal disciplinary case of efforts also ne
7、eded strengthening, individual sector and cadres also different degree exists treat gift, not to benefits not do, and mess do of phenomenon; Three for honest work is the new situations and new problems in finding timely enough, treatment measures are not strong enough. To solve these problems, we wi
8、ll proceed from the following five aspects of rectification, make sure to implement the provisions of the code. (A) deepening the learning, enhance the consciousness of honesty in politics. To create event as an opportunity to Excel and learning party, further increasing the governance capability an
9、d advanced construction, reinforced rules of the broad masses of party members and cadres awareness, sense of responsibility, sense of honor, improve working ability and level of scientific development. Should make full use of meetings, in particular central group learning opportunity, further stren
10、gthening the study and education of the code, the intensive warning education, education the majority of party members and cadres known fear, knew fear, honesty in politics of tension the strings, consciousness and enhancing the implementation of the initiative. Also, pay attention to apply what the
11、y have learned, consciously study results into planning work, new ideas,东风隧道(4#横洞)正洞反坡施工方案工期对比东风隧道3#横洞承担正洞施工任务2700米,里程为:DK646+000DK648+700,其中级围岩115米,级围岩815米,级围岩1395米,级围岩375米。到2012年10月7号,已完成135米DK646+000DK646+135,其中级围岩55米,级围岩60米,级围岩20米。剩余的任务:2565米,里程为:DK646+135DK648+700,其中级围岩60米,级围岩755米,级围岩1375米,级围岩3
12、75米。施工进度指标为级围岩160米/月,级围岩120米/月,级围岩80米/月,级围岩40米/月。从一端掘进工期为:60/160+755/120+1375/80+375/40=33.2月=996天。从两端掘进,以DK647+574为交汇里程从3#口向出口方向掘进的任务为1439米,其中级围岩60米,级围岩575米,级围岩655米,级围岩149米。掘进时间为:60/160+575/120+655/80+149/40=17.1月=513天从4#口向进口方向掘进的任务为1126米,其中级围岩180米,级围岩720米,级围岩226米。掘进时间为:180/120+720/80+226/40=16.2月=
13、486天从两端掘进总工期为17.1月(513天)。反坡施工较一端施工工期节省483天,大大提高了施工进度和效率。东风隧道(4#横洞)正洞反坡排水施工方案一、工程概况东风隧道位于弥勒石林区间,隧道进口里程DK638+769,出口里程DK650+065,全长11296m,双线隧道,左右线线间距4.7934.6m,设计为15.5的单面上坡,隧道进出口均接路基工程,最大埋深169m,洞身共穿过3段浅埋段。二、自然地理概况1、地形地貌测区属滇东南高原石林期剥夷面岩溶地貌。隧道处于岩溶高原面向弥勒盆地过度的岩溶斜坡地段,高程15061769m,相对高差约260m,自然坡度约1540,局部较陡。地表植被发育
14、,以杂木、灌木丛为主,缓坡地带少量辟为耕地,基岩零星出露。地表峰丘洼地、落水洞及孤峰平原等岩溶形态较丰富。2、地层岩性上覆第四系全新统坡洪积层及坡残积层粉质黏土、红黏土,细、粗角砾土。下伏基岩为二叠系下统梁山组灰岩夹炭质页岩、砂岩;石炭系上统马平组白云质灰岩;石炭系中统威宁组灰岩;下元古界侵入岩辉绿岩及断层角砾。3、水文地质测区地下水的主要来源为大气降水,在大平地断层处分水岭一带地势较高处接受降雨补给,区内基本无地表支流发育,只有在东风隧道的出口段才发育开口型的支沟,洞身段属地下水垂直渗流带和季节变动带。4、涌水量根据设计资料预测,隧道估算涌水量为Q=6.9104m3/d。三、方案设计与实施东
15、风隧道(4#横洞)正洞反坡施工按1100m设计,采用机械排水,由于正洞坡度较小,排水方案为正洞施工时开挖掌子面的积水通过小水泵抽到最近的聚水坑,再由主水泵由聚水坑通过水管将水抽至上级聚水坑,最终经横洞排水沟排放至洞外(见下图)。在隧道中线两侧设置聚水坑,设于综合洞室处(DK647+874/ DK648+374),聚水坑采用片石砌筑,坑内采用水泥砂浆抹面。LK-集水坑间距 is-线路坡度集水坑接力式反坡排水方式东风隧道估算涌水量为6.9104m3/d,本设计排水能力按4.2104m3/d考虑,同时考虑一定的备用水泵,两个集水坑容量按照10min涌水量设计。其中,最大涌水量暂时不予考虑,根据超前地
16、质预报等预报手段,适时增加水泵数量。临时聚水坑根据汇水段水量大小而定。工作水泵按使用1台、备用1台,并设专业排水人员管理和操作。四、设备选型配套表1 水泵配置表名称水泵型号流量m3/h扬程m功率kw出水管径mm数量台备注东风隧道(4#横洞)GMZ100-18-170渣浆泵170162215020掌子面GMZ250-32-1220渣浆泵7303722030048集水坑五、排水系统1、管路根据洞内最大水量情况,结合选配的抽水设备,正常施工采用一套为300mm管路,管材为无缝钢管。2、集水坑正洞内集水坑设在洞内左右两侧,设于综合洞室处(DK647+874/ DK648+374)。积水坑尺寸为:5m(
17、长)4m(宽)3m(深),容量60m3。3、排水供电为确保洞内排水正常进行,设置两条供电系统,一路运行,一路备用。4、其它掌子面排水采用移动式水泵,管路为150mm消防软管,抽排至就近的泵站或临时积水坑内。为保证洞内道路无水干爽,必须修建好两侧排水沟,确保洞内渗水通过侧沟引入积水坑内,不至于洞内道路上漫流。六、排水管理和实施1、人员安排队长1人、副队长1人、设备检修1人、排水工班2个班。每班组成:工班长1人,集水坑管理员1人/每坑、掌子面操作人员4人。队长陈涛副队长王炎设备检修曾茂荣人二工班长杨硕一工班长潘洪玉每个集水坑管理员1人,掌子面操作4人。每个集水坑管理员1人,掌子面操作4人。图1 反
18、坡排水人员组织机构图2、运行和检修确保电路确保电路安装的正确,检查转向是否正确;设置接地装置及标志。电泵的冷却,采用下一个泵站抽上来的水直接浇至电泵上进行冷却。施工中采用在水泵与管路的接口处安一+20 mm出水口,利用高压水不断对进水口处进行冲搅;同时,利用高压风进行冲吹,防止污泥的淤积。施工人员及时对坑内污泥杂物进行清理。在进水口仓裹铁窗纱,同时把水泵(工作面移动式)或进水口施在竹筐内,可以防止污泥及杂物的进入而发生堵塞。当水位下降超过底座,间歇出水时,应立即停机进行检查;运行一定时间后,须进行维护保养。及时地进行保养和维修是确保设备正常运转的必要措施。3、队长、副队长轮流24 h值班制,并
19、制定抽水记录表进行统一管理,发现问题及时处理,汇总问题进行总结分析。 东风隧道(4#横洞)正洞反坡爆破施工方案1.工程自然条件1.1自然地理概况1.1.1地形地貌 东风隧道区段属滇东南高原石林期剥夷面岩溶地貌。隧道处于岩溶高原面向弥勒盆地过度的岩溶斜坡地段,高程15061769m,相对高差约260m,自然坡度约1540,局部较陡。地表植被发育,以杂木、灌木丛为主,缓坡地带少量辟为耕地,基岩零星出露。地表峰丘洼地、落水洞及孤峰平原等岩溶形态较丰富。隧道进、出口有便道通过,交通较方便,洞身公路及便道稀少,相通条件较差。1.1.2气象水文 属亚热带湿润季风气候区,直接承受印度洋及太平洋水汽补给。其气
20、候特点是温暖湿润,雨量充沛,夏季长而炎热,冬季短偶有奇寒,有明显的干湿两季之分。弥勒县年平均气温为17.2,极端最高气温为36.1(1969年5月15日);极端最低气温为4.1(1999年12月27日);年平均风速为2.6m/s,最大风速为17.0m/s,风向为南南西。年平均降雨量为956.7mm,历史最大年降雨量为1326.4mm(1961年),最小为724.9mm(1963年);最大一日降雨量为144.7mm(1995年6月1日);雨季为510月,占全年降雨量的85.6%。年平均日照时数为2083.8小时。年平均蒸发量为1906.9mm。年平均雷暴日数为70天。最大积雪深为7cm(1980
21、年),年平均霜冻期为20天。相对湿度为73。1.1.3地震动参数 根据中国地震动峰值加速度区划图(GB18306-2001),测区地震动峰值加速度为0.15g。1.2工程地质特征1.2.1地层岩性 上覆第四系全新统坡洪积层(Q4dl+pl)及坡残积层(Q4dl+el)粉质黏土、红黏土,粗角砾土。下伏基岩为二叠系下统梁山组(P1l)页岩、砂岩夹灰岩;石炭系上统马平组(C3m)白云质灰岩;石炭系中统威宁组(C2w)灰岩;下元古界侵入岩()辉绿岩及断层角砾(Fbr)。1.2.2地质构造 本区跨越“扬子准地台”和“南华后加里东准地台”两个一级大地构造单元,测区地处昆明山字型构造体系东翼,隧道通过区经向
22、构造体系为主发育,另有规模较小的纬向构造与其交汇错移。主要断层为妈平断层、大额衣断层及啊基邑向斜。1.3水文地质特征1.3.1地表水发育特征 测区处于云贵高原向弥勒盆地过度的岩溶斜坡地段,隧道洞身地表无大的地表水系及迳流,局部岩溶洼地内有少量积水。地表水主要为线路右侧1.02.0Km附近在弥勒盆地边缘分布的以岩溶泉为主补给的水库(塘)水。1.3.2地下水赋存条件 主要以岩溶水为主,岩溶发育,含水充沛。次之为啊基邑向斜核部岩溶水储水构造及各断层破碎带断层水。泉点多,流量丰沛。1.4不良地质 隧道主要存在的不良地质有:岩溶、蚀变带、构造破碎带、高地应力高地温、红黏土、潜在不稳定斜坡。2.设计依据爆
23、破工艺试验的依据为:爆破安全规程(GB6722-2003)、铁路工程施工安全技术规范(TB10401.1-2003)、铁路隧道施工规范(TB10204-2002)、铁路隧道钻爆法施工工序及作业指南(TZ231-2007)、铁路隧道工程施工质量验收标准(TB10753-2010、J1149-2011)、爆破相关施工经验。3. 爆破设计方案围岩钻爆采用台阶法施工;即将隧道断面分为上下两个台阶分别实施爆破。首先开挖上台阶,上台阶完成一定进尺并进行支护后再开挖下台阶。由于上台阶的开挖为下台阶开挖增加了临空面,且为出渣、通行安全需要下台阶分左右两部交错开挖,即左边开挖时右边为通行车道,右边开挖时左边为通
24、行车道,确保上台阶正常施工。为加快进度,上下台阶可同时作业,爆破时分开爆破。3.1爆破方案选择东风隧道正洞段,施工中严格按新奥法原理组织,遵循“管超前,严注浆,短进尺,弱爆破,强支护,早封闭,勤量测” 的施工原则。根据隧道施工规范对开挖轮廓的要求,选择台阶法开挖、光面爆破方案,出渣采用装载机装渣、自卸汽车运输。上台阶开挖循环进尺级围岩不得大于一榀钢架间距,级围岩不得大于两品钢架间距,周边采用光面爆破,均采用手风钻钻孔。3.2爆破器材选用根据施工中常用爆破器材,选用以下火工品隧道的爆破器材。爆破器材名称规 格用 途雷管瞬发电雷管(8#)起爆117段非电毫秒雷管掘进和传爆炸药乳化炸药爆速38004
25、000m/s直径32mm掘 进传爆线6600m/s导爆索起爆、预裂3.3炮孔布设及爆破参数的选择与装药量的计算3.3.1炮孔布孔采用梅花形布设,周边眼延开挖轮廓线均匀布设,围岩较软时可向内偏移5-10cm。内圈眼布设满足周边眼抵抗要求,其余辅助眼交错布置在光爆层内圈眼与掏槽眼之间,周边炮眼与辅助炮眼眼底应在同一垂直面上,掏槽眼应加深10-20 cm。隧洞爆破台阶法孔位布置图。3.3.2参数选择参看附后参数表3.3.3装药量的计算参看附后参数表3.4装药方法、装药结构及炮孔堵塞3.4.1装药方法采用人工用木制(或者PVC管)炮棍装药,起爆体均在火工品加工房进行加工,起爆体必须专人加工,分段存放。
26、3.4.2、装药结构周边眼采用光面爆破,装药结构为间隔装药;掏槽孔和掘进孔、底板孔采用连续装药结构。3.4.3、炮孔堵塞炮孔采用炮泥堵塞,炮泥采用黏土和砂会和制作,炮泥应干湿适度。光面爆破周边眼堵塞长度不小于30厘米,其它炮眼深度小于1米堵塞长度不宜小于炮眼深度的1/2,深度12.5堵塞长度不小于0.5米,深度超过2.5米的堵塞长度不小于1米。3.5网络设计及起爆方法3.5.1起爆网络采用并簇连法,按如下顺序连接:孔内雷管分组周边孔导爆索并接同段非电雷管双发簇连双发瞬发电雷管起爆。3.5.2、起爆器材:孔内采用非电毫秒雷管和导爆索(周边孔)起爆,孔外采用非电毫秒雷管传爆,起爆采用双发瞬发电雷管
27、起爆。3.5.3、起爆方法:警戒完成后,利用起爆器起爆。在完成爆破后30min炮烟吹净后进入爆区检查,确认无盲炮后方可解除警戒。3.6爆破顺序光面爆破:掏槽眼辅助眼周边眼底板眼4.安全技术与防护措施1、火工品管理必须有火工品管理人员进行管理,现场火工品使用由爆破员使用,安全员现场监督。爆破完成后,剩余火工品必须全部退库,做到帐账相符,账物相符。2、工程现场100m范围内进行实地调查,记录可能影响的构筑物或其它结构状态,记录资料应包括文字和图片资料,现场可作观测标志。3、必要时可进行地表震动观测,以优化爆破设计。4、装药前电灯及电线应撤离开挖面,装药时可用投光灯、矿灯照明;5、在地下水较多的地段
28、,所用爆炸材料应能防水,连接线应采用塑料导线,敷设爆破网路时接头不得浸在水中,如不能避免时应加强接头的防水与绝缘处理。6、对进洞施工人员必须进行岩爆普及知识和安全须知的教育;。7、爆堆检查时间:对临时进洞人员也必须向其交待注意事项爆堆检查时间应在爆后30min且炮烟排出后,由熟练爆破员进行检查。8、盲炮处理:由于本次施工采用炸药均为乳化炸药,因此发生盲炮后,必须由专职爆破员进行处理。处理方法为:(1)最小抵抗线没有破坏,能够重新引爆的,加大警戒范围,重新加入起爆体引爆;(2)不能重新引爆的炮孔,采用高压风吹出堵塞炮渣,取出起爆雷管,并将炸药取出;(3)在盲炮旁边30cm处进行钻眼(钻眼与盲炮眼
29、平行)、装药起爆引爆盲炮;(4)严禁采用木棍硬捣起爆药卷。9、严禁利用残眼穿孔,以免钻爆残眼中残留炸药。10爆破警戒:(1)装药警戒范围由爆破工作领导人确定,装药时应在警戒边界设置明显标志并派出岗哨;执行警戒任务的人员,应按指令到达指定地点并坚守工作岗位。(2)洞口爆破(入洞30米内)加强警戒,以洞口为中心200米范围为警戒区,设6个警戒点。入洞30米后,警戒区重点为洞口垂直方向及发散方向,距离为300米。爆破作业人员及警戒人员也要注意避炮。11、信号:预警信号:该信号发出后爆破警戒范围内开始清场工作;起爆信号:起爆信号应在确认人员、设备等全部撤离爆破警戒区,所有警戒人员到位,具备安全起爆条件
30、时发出。起爆信号发出后,准许负责起爆的人员起爆;解除信号:安全等待时间过后,检查人员进入爆破警戒范围内检查、确认安全后,方可发出解除爆破警戒信号。在此之前,岗哨不得撤离,不 允许非检查人员进入爆破警戒范围;各类信号均应使爆破警戒区域及附近人员能清楚地听到或看到。12、为了保证岩石爆破后及时排烟,除采用自然通风外,采用单口压入式通风。13、为确保洞内爆破对衬砌模板及砼的危害,衬砌施工应待地下通道石方爆破完毕后开始施工。14、炸药、雷管、导爆管的存放要分别建库,并经有关部门批准符合有关规定。设专职库管人员24小时不间断看守,切实做好防火、防盗、防爆工作。15、建立爆破物品台帐,严格执行领发制度,设
31、监炮员跟班作业,检查每班爆破用药量,剩余炸药及时回收入库。每天进行帐物核对.东风隧道4#横洞工程反坡双向施工通风专项方案1 工程概况东风隧道位于弥勒至石林区间,隧道进口里程DK638+769,出口里程DK650+065,中心里程DK644+417,全长11296m,双线隧道,左右线线间距为4.7934.600,设计为15.5的单面上坡,隧道进出口均接路基工程,最大埋深169m,洞身共穿过3段浅埋段。为加快施工进度,解决施工及运营期间排水以及改善施工通风条件,结合地形、地质条件,本隧设置“四横洞”辅助坑道模式。四座横洞均采用无轨单车道运输,其中四号横洞长472m。 2 通风设计依据施工通风是隧道
32、施工的重要工序之一,合理的通风系统、理想的通风效果是实现隧道快速施工、保障施工安全和施工人员身心健康的重要保证。根据以往隧道通风经验及对当前通风设备技术性能的调研结果,按照自成体系的原则,综合考虑施工过程中可能出现的情况,制定隧道通风方案。2.1 通风设计依据 东风隧道4#横洞工程施工图;高速铁路隧道工程施工技术指南铁建设2010241号;铁路隧道工程施工安全技术规程(TB10304-2009);2.2 通风设计标准隧道在整个施工过程中,作业环境应符合下列职业健康及安全标准:空气中氧气含量,按体积计不得小于20%。粉尘容许浓度,每立方米空气中含有10%以上的游离二氧化硅的粉尘不得大于2mg。每
33、立方米空气中含有10%以下的游离二氧化硅的矿物性粉尘不得大于4mg。有害气体最高容许浓度:一氧化碳最高容许浓度为30mg/m3;在特殊情况下,施工人员必须进入开挖工作面时,浓度可为100mg/m3,但工作时间不得大于30min;二氧化碳按体积计不得大于0.5%;氮氧化物(换算成NO2)为5mg/m3以下。隧道内气温不得高于28。隧道内噪声不得大于90dB。隧道施工通风应能提供洞内各项作业所需的最小风量,每人应供应新鲜空气4m3/min。根据东风隧道通风设计及隧道的断面尺寸,在2#横洞与3#横洞工区贯通前现场选用75kw2的压入式通风,贯通后采用巷道式通风,通风机装设在洞外新鲜风流中,避免污风循
34、环。隧道内选用1.8m的双抗风管向洞内掌子面送风,为了保证掌子面空气的新鲜且爆破时风管不被损坏,风管距掌子面的距离应控制在30-50m。3 风量和风压计算3.1计算参数根据规范要求,确定一下参数:供给每个人的新鲜空气量按3m/min;控制通风计算按开挖爆破一次最大用药量420kg;放炮后通风时间按30min;软式风管百米漏风量1.0%,风管内摩擦系数为0.01;洞内风速不小于0.25m/s;隧道内气温不超过28。3.2 风量计算按洞内允许最低风速计算风量:Q160AV=601300.25=1950(m3/min)式中:V-洞内最小风速0.25m/sA-洞内开挖断面,取130m2洞内施工最多人数
35、按60人计Q23601.2=216(m3/min),安全系数k=1.2按爆破时最多药量计算风量:Q35Gb/t=542035.35/30=2474.5(m3/min)式中:G-同时爆破的炸药用量420kgb-爆炸时有害气体成量,取35.35t-通风时间,取30min取以上最大值2474.5m3/min作为工作面所需风量,实际所需风机风量Q机要大于:Q机=pQ=1.792474.5=4429m3/min式中: Q机- 计算最大风量, 4429m3/minp-系统漏风系数,p=1/(1-1/100p100)=1.79所需风机压力计算:使用风管直径1.5m,风管平均流速V=18.9m/s风管内摩擦阻
36、力h1=(L/D)(V2/2)=1429Pa-摩擦系数,根据使用经验、取0.01L-通风管长,取1000mD-风管直径,取D=1.5m-空气密度,取=1.2kg/m3风管内局部阻力h局=(V2/2),按风管内局部阻力h1的5%考虑,总阻力h=1429105%=1500Pa4通风设备表1每个横洞配备风机及参数表风机型号供风量(m3/min)功率(KW)风压(Pa)数量(台)备注SDF(C)-NO11.515502920752535513781SDF(C)-NO11.515502920752535513781备用5 施工通风检测为保证施工的环境良好,东风隧道3#横洞隧道建立测风制度,每10天进行1
37、次全面测风。对掘进工作面和其他用风地点,应根据实际需要随时测风,每次测风结果应记录并写在测风地点的记录牌上。应根据测风结果采取措施,进行风量调节。必须有足够数量的通风安全检测仪表。仪表必须由国家授权的安全仪表计量检验单位进行检验6 施工通风安全措施61 施工通风安全管理措施以“合理布局,优化匹配,防漏降阻,严格管理、确保效果”20字方针,作为施工通风管理的指导原则,强化通风管理。6.1.1 施工通风安全组织机构1、隧道施工项目经理部必须建立以项目经理为第一责任人的安全生产管理机构。2、建立以岗位责任制和奖惩制为核心的通风管理制度和组建专业通风班组,通风班组全面负责风机、风管的安装、管理、检查和
38、维修,严格按照通风管理规程及操作细则组织实施。项目部定期根据通风质量给予通风班组兑现奖惩办法。6.1.2 施工通风主要岗位风险管理标准及管理措施1、测风员风险管理标准及管理措施作业环境不完好;测风地点不符合规定,人员操作不熟练;测量数据记录不准确或测风报表填写不正确。管理标准:测风时,测风员根据风速的大小选择相应量程的风表进行测风。隧道每10天至少进行1次全面测风,测风地点、位置、测风周期必须符合有关规定。管理措施:分工区管理人员随时对测风员测风时选择的风表进行检查,发现选择的风表不符合规定,进行处罚。测风员必须经过培训,取得安全技术工种操作资格证后,持证上岗。熟悉所用风表和其它仪器的性能和参
39、数。熟悉隧道通风系统,掌握各用风地点所需风量。利用班前会教育员工遵守纪律、增强时间观念。2、主要通风机司机风险管理标准及管理措施主要危险源:操作高压电气设备时,未按要求佩戴绝缘用具。未对风机主要部位进行详细检查。未按开停机顺序操作。管理标准:必须经过培训并考试合格持证上岗。熟悉通风机结构性能、工作原理、技术特征、供电系统和控制回路,以及通风系统和各风门的用途等情况,能独立操作。作业前必须进行本岗位危险源辨识。遵守劳动纪律,认真填写工作日志,不做与本职工作无关的事情。当主要通风机发生故障停机时,备用通风机必须在15min内启动,并正常运转。管理措施:不得随意变更保护装置的整定值。操作高压电气设备
40、时应用绝缘工具,并按规定的操作顺序进行。除故障紧急停机外,严禁无请示停机。严格按照上级命令进行通风机的启动、停机操作。 6.1.3 通风管理制度1、 一般规定风机操作人员必须经过培训、考核合格后方能上岗作业,必须严格遵守风机的操作规程,熟悉通风系统性能。隧道通风系统必须经过验收合格后方可投入正常运行,运行期间应加强巡视及维护工作,保证通风系统各项性能、技术指标达到设计要求。保证隧道24小时连续不间断通风,风量、风压必须满足规范和施工组织设计要求,不得随意停风。风机设置两路电源并装设风电闭锁装置,确保正在使用的通风机出现故障后能在15min内启动备用通风机,保证隧道通风和正常作业不受影响。2、通
41、风系统定期检查制度作业队组织每周对通风系统进行检查,架子队长每天对通风系统必须作例行检查,通风工必须做好日常巡查。通风系统运行正常后,每10天进行一次全面测风,对掌子面和其他用风地点根据需要随时测风,做好记录。每7天在风管进出口测量一次风速、风压,并计算漏风率,风管百米漏风率不应大于1%,对风筒的漏风情况必须及时修补。建立通风系统运行管理档案,档案包括各种检查记录、调试记录、测量记录、维护记录、运行记录等。值班人员每天按班组对通风系统运行情况进行记录,架子队长每天、主管副经理每周分别对运行记录予以审核、签认,并由物设部负责建档保存。周用风速测定仪对风速进行人工检测,检测结果与自动监控系统相应时
42、间、位置、风速值进行核对,确保风速满足施工要求且回风巷风速不得低于1m/s。3、通风管理交接班制度必须实行通风班组交接班制度,交接双方签字认可,对上一班存在的问题、隐患、需注意事项、仪器设备状态等必须交接清楚,交接班记录由架子队长每天定时予以审核签字。6.2.1 风机安装风机支架应稳固结实,避免运行中振动,风机出口处设置加强型柔性管与风管连接,风机与柔性管结合处应多道绑扎,减少漏风。通风机前后5m范围内不得堆放杂物,通风机进气口应设置铁箅,并应装有保险装置。当巷道内的风速小于通风要求最小风速时,可布设射流风机来卷吸升压,提高风速。洞内风机的移动,采用小平板车移动,移动前,提前做好风机支座或支架
43、。射流风机应逐个移动,以保证洞内不间断的空气循环。通风机应有适当的备用数量。6.2.2 风管安装风管必须有出厂合格证,使用前进行外观检查,保证无损坏,粘接缝牢固平顺,接头完好严密。通风管应优先采用高强、抗静电、阻燃的软质风管。风管挂设应做到平、直,无扭曲和褶皱。在平行导坑作业时,先由测工在拱顶测出中线位置,然后用电钻打眼,安置膨胀螺栓;在正洞作业时,衬砌地段根据衬砌模板缝每5m标出螺栓位置,未衬砌地段,先由测量工在边墙上标出水平位置,然后用电钻打眼,安置膨胀螺栓。布8号镀锌铁丝,用紧线器张紧。风管吊挂在拉线下。为避免铁丝受冲击波振动、洞内潮湿空气腐蚀等原因造成断裂,每10m增设1个尼龙绳挂圈。
44、通风管破损时,应及时修补或更换。当采用软风管时,靠近风机部分,应采用加强型风管。通风管的节长尽量加大,以减少接头数量,接头应严密,每100m平均漏风率不宜大于1%。弯管平面轴线的弯曲半径不得小于通风管直径的3倍。风管最前端距掌子面5m,并且前55m采用可折叠风管,以便放炮时将此55m迅速缩至炮烟抛掷区以外。6.2.3 通风系统日常管理和维护措施通风机应有专人值守,按规程要求操作风机,如实填写各种记录。通风机使用前应卸去废油,换注新油,以后每半月加注一次。风机应尽量减少停机次数,发挥风机连续运转性能。需停机或开启时,根据洞内调度通知进行。为减少风机启动时的气锤效应对风管的冲击破坏,应采用分级启动
45、,分级间隔时间为3min。开启轴流风机前,射流风机必须开启运转,以控制风流方向,防止污浊空气形成小循环。综合保障班组中应设专职风管维修工。每班必须对全部风管进行检查,发现破损等情况及时处理。对于轻微破损的管节,采用快干胶水粘补:先将破损部位清洁打毛后,再行粘补;破损口小于15cm时,直接粘补;破损口大于15cm时,先将破口缝合后再行粘补,粘补面积应大于破损面积的30%。粘补后10min内不能送风。对于严重破损的管节,必须及时更换。因洞内渗水和温度变化的影响,风管内会积水,故应定期排水,以减少风管承重和阻力。new measures to promote work, the courage to
46、 take responsibility, dare to break hard to ensure district, Government decisions and arrangements to implement. (B) strengthening supervision, severely punish acts of violation. One is to open the channels of supervision. Vigorously promote the party affairs public, open, widely accepted supervision by the masses, pay attention to social groups and public opinion supervision, the powerful force formed to urge party members and leading cadres properly exercise their powers. Second, strong supervision and inspection. Democratic life in