1、Company NameCompany Group, Division, LocationDocument Title: Incoming InspectionDocument Number:Document NumberDocument Filename:Document FilenameCONTROLLED COPY/ MASTER COPYSTAMP HEREOTHERSTAMP HERERevision LevelRevision DateDCO/ECONumberDescription of RevisionRevision AuthorDRAFTDD/MM/YYYY-00000Dr
2、aftAuthor Name1.00DD/MM/YYYY-00000Initial ReleaseAuthor NameTable of Contents1.0Purpose32.0Scope33.0Definition Of Terms33.1Goods33.2Production Material33.3Process Material33.4Inspection Criteria34.0Responsibilities34.1Quality Assurance (QA)34.2Shipping/Receiving34.3Engineering35.0References36.0Proce
3、dure46.1First Article Inspection (if applicable)46.2Documentation Verification46.2.1Verify Engineer Drawings and Specifications46.2.2Verify Material Identification Label Accuracy46.2.3Verify Certification Receipt and Accuracy46.2.4Verify Markings and Packaging46.2.5Verify Approved Supplier Status46.
4、2.6Verify Receipt Record (RR) Accuracy and Completeness56.2.7Verify Expiration Date56.3Inspect Material56.3.1Material Inspected at the Supplier56.3.2Inspect at Incoming Inspection56.3.3Accept56.3.4Reject56.3.5Release Prior to Inspection56.4Disposition66.4.1Accepted Material66.4.2Rejected Material67.
5、0Flow Chart77.1Incoming Inspection Flow Chart78.0Appendix88.1Guidelines for Writing Inspection Criteria81.0 PurposeThis document establishes an inspection system and documentation requirements for incoming (received) material requiring inspection.2.0 ScopeThis procedure applies to production and pro
6、cess material received at the facilities of Company Name. This procedure also may be applied to other received materials at the discretion of the Purchasing Requisitioner.3.0 Definition Of Terms3.1 GoodsMaterial with utility and/or intrinsic value purchased by, internally produced by, and/or supplie
7、d to a company.3.2 Production MaterialMaterial that becomes part of a shippable product.3.3 Process MaterialMaterials that are required in the manufacturing process, but do not become part of the shippable product.3.4 Inspection Criteria The criteria used to inspect and accept or reject production a
8、nd process material. Inspection Criteria must define the attributes or features to inspect, the sampling plan, and the accept/reject criteria.4.0 Responsibilities4.1 Quality Assurance (QA)Quality Assurance is responsible for the timely inspection of incoming material, and for notifying Inventory whe
9、n incoming inspection is complete. Quality Assurance is also responsible for determining incoming material Inspection Criteria which are adequate and appropriate for the material being inspected, taking into account recommendations from engineering.4.2 Shipping/Receiving Shipping/Receiving is respon
10、sible for all normal receiving activities, including material receipt, creation of a Receipt Record (RR), and location of material requiring inspection at incoming inspection (along with all certifications, test results and other related documentation for the shipment). When material requiring incom
11、ing inspection has been received, Receiving moves it to Incoming Inspection.Shipping/Receiving is also responsible for moving and properly locating material after inspection, based on inspection results.4.3 EngineeringEngineering is responsible for recommending key attributes to inspect for all comm
12、ercial items and customdesigned items released by Engineering.5.0 ReferencesMaterial Review BoardFirst Article InspectionAcceptance Sampling PlansQuality RecordsPart History RecordFirst Article Inspection Data SheetInspect Inquiry for Non-Inventory Parts6.0 ProcedureNote: Before opening any packages
13、 and handling material review and follow all handling precautions in the Inspection Criteria for the material.When notified that material that requires inspection has been received, gather relevant documentation for the material, which may include Inspection Criteria, Component Specification, Purcha
14、se Order, Vendor History, and Certificate of Compliance or Test. Documentation may be paper or electronic format.6.1 First Article Inspection (if applicable)If first article inspection is required, perform according to the First Article Inspection procedure. See that procedure for guidelines on when
15、 to perform first article inspection.If first article inspection is not required, continue with this procedure.6.2 Documentation VerificationBegin an Inspection Report (First Article or Part History Record) for the material. Record Item Number, Item Description, Revision (if applicable), Date Receiv
16、ed, Quantity received, Lot Number, Purchase Order (PO) Number, Supplier ID, and Inspection Document(s) and revision. Record the following documentation verification results on the Inspection Report.6.2.1 Verify Engineer Drawings and SpecificationsVerify that the engineering drawings and specificatio
17、ns used for inspection are at the appropriate revision level.6.2.2 Verify Material Identification Label AccuracyCompare the documentation and the material received to the Material Identification Label(s), to assure that each label is accurate. Have Shipping/Receiving correct any label discrepancies.
18、6.2.3 Verify Certification Receipt and AccuracyVerify that material certification was received. Assure that the certification matches the material received. Notify Purchasing immediately if certification is missing or incorrect as required. QA will contact the vendor and request a faxed copy of the
19、certification. Reject material for which certification cannot be obtained.6.2.4 Verify Markings and PackagingVerify all material markings and/or packaging required by the Drawing, Component Specification or Purchase Order.6.2.5 Verify Approved Supplier StatusVerify that the material was purchased fr
20、om an approved supplier. Verify that manufacturer and manufacturer part number and/or supplier and supplier part number are identical to those listed in the Component Specification.6.2.6 Verify Receipt Record (RR) Accuracy and CompletenessVerify that the attached Receipt Record is accurate and compl
21、ete.6.2.7 Verify Expiration DateFor material with a finite shelf life, verify that the correct expiration date has been recorded on each package. Record the expiration date on the Part History Report or First Article Inspection Report.6.3 Inspect Material6.3.1 Material Inspected at the SupplierA Com
22、pany Name onsite inspector or Quality Assurance may inspect and accept material at the supplier prior to shipment to Company Name. Any such material received properly labeled as Accepted and accompanied by (or received separately) a completed Part History Record or First Article Inspection Report fr
23、om the inspector, has passed incoming inspection and need not be reinspected. Go to Disposition of Accepted Material in this procedure to properly disposition material accepted at the supplier.6.3.2 Inspect at Incoming InspectionInspect the material according to its Inspection Criteria.Inspection Cr
24、iteria are found in the Part History File and may be determined by Quality Assurance and/or Engineering. Randomly select any samples. Record inspection results on the Inspection Report, attaching additional sheets as necessary, and numbering each sheet Page _ of _.” Highlight any nonconformities.6.3
25、.3 AcceptA shipment of material is accepted if Document Verification is satisfactory, and the material meets or exceeds all of the acceptance criteria in the Inspection Criteria. For sample inspection, acceptance criteria is met if the number or percentage of nonconformities found in the sample is l
26、ess than or equal to the acceptance number for the sampling plan. Disposition as nonconforming material any sample material found with nonconformities.6.3.4 RejectA shipment of material is rejected if Document Verification is not satisfactory, or if the material does not meet one or more of the acce
27、ptance criteria in the Inspection Criteria. For sample inspection, acceptance criteria is not met if the number or percentage of nonconformities found in the sample is greater than or equal to the rejection number for the sampling plan.6.3.5 Release Prior to InspectionIn rare instances, a shipment o
28、f material will be needed by production before incoming inspection is complete. At the discretion of the Quality Assurance Director, part or all of the shipment (less samples retained by Quality Assurance for inspection) may be released to production, providing a positive recall system is in place t
29、o identify and recover the shipment if it is rejected when inspected. Lot tracing the shipment to all stocking locations and assemblies is one positive recall method.6.4 Disposition6.4.1 Accepted MaterialComplete the Inspection Report and Receipt Record, including quantity accepted, quantity rejecte
30、d, page numbering. Date, initial, and stamp the report. Attach material certifications to the report if applicable.Status the material Accepted by attaching the appropriate material label and making entries in Dataworks.Retain (file) the Inspection Report and the Supplier History Form (ref QualityRe
31、cords).Move material to inventory as required. 6.4.2 Rejected MaterialComplete the Inspection Report, including quantity accepted, quantity rejected, NCMR number (see Material Review Board procedure), page numbering, and date and initial the report. Attach material certifications to the report.Compl
32、ete a manual NCMR form.Status the material Rejected by attaching the appropriate material label and making entries in Dataworks.Record the electronic NCMR number (from Dataworks) on the manual NCMR form.Retain (file) the Inspection Report and the Supplier History form (ref Quality Records). Note: Re
33、jected incoming material will be dispositioned by the Material Review Board (MRB). Since the Inspection Report contains information needed by the MRB, to save time, MRB paperwork may be initiated before filing the Inspection Report.Rejected material must be quarantined in the MRB room. 7.0 Flow Char
34、t7.1 Incoming Inspection Flow Chart8.0 Appendix8.1 Guidelines for Writing Inspection CriteriaInspection Criteria are to verify that material meets engineering specifications. Inspection Criteria cannot impose new design requirements or workmanship standards on the material.Engineering and Quality En
35、gineering are responsible for writing Inspection Criteria and to: Select the attributes to be inspected and the sampling plan for each attribute. See Acceptance Sampling Plans for the list of available sampling plans. Select or recommend inspection equipment and conditions. For material that may be
36、damaged by handling or storage during inspection (i.e. static, temperature, or humidity sensitive material, or clean material), handling precautions must be specified. When selecting attributes to inspect, focus attention on key attributes. For example, for a mechanical component, key attributes may
37、 be dimensions with the tightest tolerance, or dimensions which interact with mating components. Engineering is responsible for initially recommending attributes to inspect. All product labeling (labels, inserts, physicians manuals, registration cards, etc.) must be, at a minimum, sample inspected.
38、Inspection Criteria for customer supplied or furnished material will be written. Unless Company Name has agreed to provide inspection services for the customer, only customer accepted material will be supplied to Company Name. Therefore, Company Names inspection will consist of checking for shipping
39、 damage and verifying proper material identification.Inspection Criteria are documented by one of the following: An Inspection Instruction A Component Specification with an Inspection Criteria section A printout of the current revision of a drawing, markedup to indicate the attributes to inspect and the sampling plan for the attributes. The markedup drawing is created and signed by Engineering and Quality Engineering, and is maintained in the incoming inspection file folder.