1、工商管理施工成本中英文对照外文翻译文献 中英文翻译 The Contractors Role in Building Cost Reduction After Design It has become evident from recent news articles that inflationary pressures and increased construction activity are causing many building projects to come in well over owners budgets. This trend has increased dram
2、atically over the past few years, as much of the construction industry has been impacted by an unprecedented increase in the cost of construction. The historical rate of increase in construction cost has been under five percent per year, as reported by the Engineering News Record . Over the last few
3、 years, the industry has seen a significant increase from historical escalation rates, up to 10-15 percent per year in many regions of the US. These increases have been caused by a variety of factors, including the following. Shortage of steel resulting from rapid growth in China. Demand for materia
4、ls in the US resulting from increased hurricane damage. Rising oil prices leading to higher manufacturing and transportation cost. Rising labor cost because of increased construction activity . To be successful in having over budget projects awarded, the building contractor has had to take a proacti
5、ve role in working with owners and design teams to reduce project cost to amounts that owners are able to award. This cost reduction is normally accomplished through the following methods. value engineering; scope reduction; Value Engineering Value engineering (VE) has been defined as a systematic m
6、ethod to improve the value of goods and services by using an examination of function. Value, as defined, is the ratio of function to cost. Value can therefore be increased by either improving the function or reducing the cost. It is a primary tenet of value engineering that quality not be reduced as
7、 a consequence of pursuing value improvements . VE is a process originating at General Electric Company (GE) during World War II. Because of shortages of skilled labor, raw materials, and component parts, engineers at GE looked for acceptable alternates and often found substitutions that resulted in
8、 reduced costs and/or product improvement. GE developed a systematic process that they called value analysis. Over the years the name gradually changed to VE. The basic steps of VE include the following: Information gathering: project requirements defined, function analysis. Alternates: various ways
9、 of meeting the requirements and functions. Evaluation: assessment of alternates on how well they meet requirements and costs savings. Presentation: selection of best alternatives to be presented to client for decisions. True VE evaluates life cycle costs such as initial cost, maintenance cost, oper
10、ational cost, life span, time value of money, replacement cost, and frequency of replacement. VE can be undertaken at any stage of the building design process; however, it is most effective in the early stages, since it is less costly to make changes to preliminary documents . Scope Reduction Scope
11、reduction involves identifying areas of the project scope of work that can be reduced in quality, quantity, or both in a manner that is acceptable to the owner. Scope reduction items of work often consist of material or equipment substitutions that lower the cost of the project, but may not be an eq
12、ual substitute. An example of quantity scope reduction would be to reduce the guttering system on a pitched roof from the entire roof perimeter to entrances only. A quality scope reduction example would be to provide vinyl composition floor tiles (VCT) in lieu of ceramic floor tiles. After a project
13、 has been determined to be out of budget because of high bids, the project is normally either cancelled, redesigned and re-bid, or negotiations are held with the low bidder to reach an acceptable contract amount. For the building contractor that is selected for negotiations, this is an opportunity t
14、o move toward project award and to also build a relationship of trust and openness with the owner and design team that could lead to future projects. First, the building contractor should meet with the owner and design team to fully understand the owners project requirements, priorities, life cycle
15、considerations, and budget. Next, the building contractors role is to use his estimating and construction expertise to analyze various components and systems within the project for alternate solutions. The contractor should also bring in key subcontractors and suppliers who are often able to identif
16、y alternate materials and/or systems within their specialties. Each division of work should be examined and evaluated for VE solutions. In past years, this process and service was considered part of the building contractors overhead. However, in todays market, some contractors will negotiate rates a
17、nd be reimbursed for the time and effort that they spend in this process in the event that the project is not awarded to them. The work breakdown structure (WBS) can be a helpful tool to the building contractor in analyzing the various components and systems within a building project. The WBS is a t
18、ree-type structure of functional systems used to classify the project on a level-by-level basis . This breakdown structure facilitates the evaluation of each system of the project from the building foundations to the completed sitework. Questions to Ask or Areas and/to Consider by WBS This section p
19、rovides a list of areas for the building contractor to examine and/or questions to ask in the WBS system level format for cost saving alternatives. Some of these changes can be accomplished without major re-design cost and incorporated into the construction documents in the form of an addendum. Othe
20、r changes listed would require extensive re-design and time delays. SUBSTRUCTURE Have alternate types of foundation system been considered? wood piles in lieu of precast; drilled caissons vs. piles; mat foundations in place of piles or caissons. Evaluate sand base in place of gravel or stone under s
21、lab on grade. SUPERSTRUCTURE Have alternate types of building structures been evaluated? structural steel, precast concrete, cast in place concrete, light gauge steel framing or wood framing systems. Compare Alternate Stair Systems. steel pan stairs vs. precast concrete or cast in place concrete. EX
22、TERIOR CLOSURE Evaluate exterior wall systems. Light gauge metal framing in lieu of reinforced concrete masonry units. Can wall widths or gauges be reduced? Compare sheathing systems. Fiber sheathings in place of cement boards. Review alternate wall insulation systems. Batt insulations, rigid insula
23、tion materials, loose fill block insulation. Consider alternate exterior wall veneers. Conventional stucco versus exterior insulation finish system. Brick or precast in lieu of stone. Evaluate alternate glazing systems. Can exterior glazed areas be reduced? Storefronts in lieu of curtainwalls if cod
24、e allows. Painted aluminum in lieu of stainless steel or brass framing. Review exterior entrances. Manual entrance doors in place of automatic entrances. Automatic entrances in lieu of revolving doors. Cedar entrance doors rather than mahogany. Examine exterior railing systems. aluminum or cable sys
25、tems in lieu of glass; standard designs in place of custom elements; ROOFING Evaluate the specified roofing with alternative materials. Combined metal decking/insulation systems in lieu of separate systems. Interior batt insulation in place of rigid roof insulation. Built-up roofing vs. single ply m
26、embranes. Fiberglass or concrete tiles in lieu of clay tiles. Painted metals in place of copper. Can the specified gauge of metal roofing be lowered? Eliminate or reduce the guttering system? Can skylights be reduced or styles changed? Are standard warranties specified? INTERIOR CONSTRUCTION Examine
27、 interior wall systems. Can light gauge metal-framed walls be used in lieu of concrete masonry units? Can wall thicknesses or gauges be reduced? Are drywall systems being used in lieu of plaster? Examine interior doors and hardware. Are the specified doors standard sizes or custom? Have alternate wo
28、od door species been considered? Have alternate hardware styles or manufacturers been compared? Can manual doors be used in lieu of automatic? Are the doors pre-machined for hardware installation? Compare pre-finishing doors with finishing on-site. Review interior specialties. Have alternate types o
29、f toilet partitions been considered? Prefinished metals vs. plastic laminates. Can vinyl corner guards be used rather than metal? Metal lockers vs. wood. Have special partitions been evaluated? Plastic veneers in lieu of wood. Can the sound rating be reduced? Defer installation? Has the access floor
30、ing system been evaluated? Standard floor finishes rather than custom? INTERIOR FINISHES Evaluate interior wall finishes. Painted wall finishes in lieu of wallcovering. Epoxy coatings in place of tile finishes. FRP instead of stainless steel. Are textured drywall systems being used rather than plast
31、er? Examine interior floor finishes. Resilient flooring vs. ceramic or wood. Ceramic flooring in lieu of stone. Tile or stone in place of terrazzo. Alternate carpet manufacturers. Review alternate ceiling finishes. Standard ceiling vs. custom. Fiber ceiling vs. metal. CONVEYING SYSTEMS Review specif
32、ied elevators and escalators. Have alternate manufacturers been considered? Are standard interior elevator cab finishes specified or custom? Can glass walls be eliminated? Are standard warranties specified? SITE PREPARATION Has a site work analysis been performed to balance cuts and fills. SITE IMPR
33、OVEMENTS Can paved areas be reduced or more economical paving materials used? Has resurfacing existing parking areas been considered rather than new parking construction? Have alternate types of enclosure walls been considered? Have landscaping alternatives or substitutions been considered? Seeding
34、in place of sodding. Reduce or change tree and plant materials. Use existing trees and other existing landscaping. SITE CIVIL/MECHANICAL UTILITIES Have alternate utility piping materials been evaluated? Can existing site utilities be abandoned rather than removed? SITE ELECTRICAL UTILITIES Have alte
35、rnate exterior lighting packages been compared? Have alternate utility piping materials been evaluated? CONTRACTOR OVERHEAD AND PROFIT Can phasing be reduced to shorten the project duration? Can the start of the project be timed to avoid cost impact of winter conditions? For high-rise projects; have
36、 crane and hoisting options been compared? Can the Owner include the Builders Risk policy?. Breaking down and analyzing the components of a building project through the work breakdown structure can aid in reduction summaries also reveal that the mechanical, electrical and plumbing(MEP) systems typic
37、ally offer the greatest opportunity for cost savings due to their total significance to a project. The MEP systems normally make up between 30 to 50 percent of a building projects cost.The owners of the illustrated projects accepted cost reducing changes ranging from 6 to 14 percent of the original
38、low bids. These reductions allowed them to meet their particular budgets and have their projects constructed by incorporating the changes into addendums. Some projects may be so far over budget that substantial structural and/or building redesigns are unavoidable. However, building contractors can p
39、lay a major role in bringing projects into budgetusing their past experience along with their subcontractor and supplier networks to develop cost reduction alternatives that may not have been previously considered by owners and/or design teams. 设计阶段后承包商在降低施工成本方面所扮演的角色 从最近的新闻报道中可以明显的看出,通货膨胀的压力和建筑产业的不
40、断发展使很多工程项目超出了业主的预算。在过去几年中这一趋势急剧增加,许多建筑行业都受到成本增加的冲击。正如Engineering News Record所报道的,以前工程成本每年的增长率在5%以下。在过去的几年中,美国很多地区的建筑行业的成本的增长率已经从历史的水平迅速增加到每年10%-15%。这种增加受到很多因素的影响,包括: 中国的快速发展导致钢材的供应不足。 飓风所造成的危害导致美国材料需求的增长。 石油价格的上涨导致很高的生产和运输成本。 建筑行业的发展导致劳动力成本的上涨。 为了成功地使超过预算的项目获得业主的奖励,承包商必须积极的与业主和设计单位合作沟通来降低项目成本以达到业主可以
41、奖励的范围。实现成本的降低通常可以采用以下方法: 价值工程 缩小项目成本支出的范围 价值工程 价值工程被定义为一种提高商品和服务的价值并降低成本的系统的方法。也就是功能比上成本。价值增加不仅可以通过提高功能还可以通过降低生产成本来实现。 价值工程的一个主要宗旨是,在追求价值提高的过程中不降低产品的质量。VE起源于二战期间美国通用电气公司。由于缺乏有技术的劳动力、原材料和零部件,通用公司的工程师不断变换探索,发现了降低成本或者提高产品质量的方法。 通用公司开发了一种称为价值分析的过程体系。在过去的几年里,这个名字已经逐渐改变成为VE。VE的基本步骤包括以下几个方面: 信息收集:定义项目的需求、进
42、行功能分析。 方法:各种可以满足要求和功能的方法。 评估:评估各种方法对于满足需求和降低成本的程度。 表述:选择最好的方法提供给客户以帮助他们做决定。 VE评估的生命周期包括初始成本、维修成本、运营成本、产品的寿命、货币时间价值、重置成本以及替换的频率。VE可以应用于建筑设计的任何阶段,然而,在早期最为有效,因为更改初步设计文件的花费更少。 缩小项目成本支出的范围 缩小支出范围包括在业主可接受基础上降低质量水平、减少数量或者两者同时减少。 缩小支出范围往往在于替换材料或设备以降低项目成本,但是并不意味着是平等替换。比如说减少整个屋顶外围斜屋顶上的排水系统就是一个减少数量的例子;用乙烯组成的瓷砖
43、替代普通的瓷砖就是为了说明降低质量水平来达到缩小范围的目的。 当投标报价超过项目预算时候,通常情况下该项目要么被取消,重新设计和招标,或者让业主与低价投标者进行协商达成双方都可接受的合同价。对于被选中参加协商谈判的承包商来说,这是一个获得项目的机会,同时也是与业主和设计单位建立信任、公开化关系的机会。 首先,承包商应该与业主和设计单位洽谈,充分了解业主对项目的要求,他们考虑的首要因素、项目的生命周期和预算。 其次,承包商的角色就是要利用他们在估算和施工方面的专业知识来分析项目内各组成成分和体系,从而找到方案。承包商也应该让主要的分包商和供应商参与进来,他们往往可以在自己专业的领域范围内确定可替
44、代的材料和体系。项目工作的每个决定应该通过价值工程方法的检验和评估。在过去几年中,这个过程和服务是承包商增加支出的一部分。然而,在当今的市场上,一些承包商会通过价格谈判来补偿没有中标时他们所花费的时间和精力。 对承包商来说,工作分解结构图在分析建筑工程各个部分和系统中是一种非常有用的工具。WBS是一种将项目分为最基本组成成分的树状结构图。这种分解结构图对项目从地基基础到全部完工的各个部分的费用估算带来很大的便利。 通过WBS图来发现问题和/或者找出需要考虑的地方 这个部分向承包商提供了需要审查和/或提出问题的地方,这是建立在WBS图基础上来降低施工成本。这些变化中有些可以不用增加设计变更的成本
45、来实现,而是通过附录的形式并入建设合同中。在所列的这些范围中有些需要大量的设计变更并导致工期延误。 地基基础 -考虑能否由其它类型的基础来替代? 用木桩来替代预制桩 采用箱形基础还是桩基础 用基础垫层来取代桩基础或者箱形基础 -评估在地平面下是否可以用沙来替代砾石或者石块 上部结构 -可替代的建筑结构类型是否已经被考虑? 结构钢,预制混凝土,现浇混凝土铸造,轻钢框架或木框架系统 -比较不同形式的楼梯 钢结构楼梯、预制装配式楼梯或者现浇式钢筋混凝土楼梯 外墙幕墙 -评价外墙结构 用轻金属框架来替代钢筋混凝土砌块 墙的宽度或者尺寸能否减少? -比较建筑外围护结构 用纤维来替代水泥板 -比较墙体不同
46、的隔热构造 棉质保温材料,硬质保温材料,松散填充的保温砌块 -考虑不同的外墙装饰类型 比较传统的粉灰泥和外墙保温涂层 用砖或者预制混凝土来替代石材 -比较不同的玻璃装配方式 能否减少外墙玻璃安装的区域 在合理范围内用橱窗来替代幕墙 涂漆的铝制品来替代不锈钢或者黄铜材料的框架结构 -外部的入口 用手动的进入系统来替代自动的入门系统 用自动的入门系统来替代旋转门 用雪松质地的大门而不是红木大门 -比较不同的外部栏杆 铝制材料或者缆索来替代玻璃栏杆 使用标准设计来替代习惯性的使用元素 屋面 -评估不同材料的屋顶 混合金属的装饰/保温系统替代单一金属系统 弹性的屋面保温系统来替代刚性屋面保温系统 比较
47、内置式屋面和单一厚度的模板 用玻璃纤维或者混凝土砖来替代粘土砖 用有色金属来替代铜 是否可以减少特定规格金属屋面的尺寸 排除或者减少排水系统? 天窗是否可以减少或者变换样式 标准是否是确定唯一的? 室内建造 -审查内墙系统 轻金属的框架墙能否替代混凝土砌块 墙的厚度或者尺寸能否减少 能否用干燥墙体的系统来替代石膏?检查室内的门和硬件 使用标准尺寸的门还是习惯尺寸的? 有没有考虑使用木质门 有没有对硬件的制造商做了比较 能否用手动的门来替代自动门 门能否事先安装好硬件 比较预制精轧门和现场安装 -审查室内的特定部分 是否已经考虑了厕所分割的不同类型 比较预制金属和塑料薄层 可以用乙烯基而不是金属
48、 比较金属储物柜和木质储物柜 特殊的部分是否已经被评估 用塑料贴面来替代木质的 能否可以降低声音频率 是否需要推迟安装 是否已经评估了进入的地面系统 使用标准底面还是习惯性的 室内装修 -评估内墙装饰面 用彩绘墙壁饰面来替代墙纸 用环氧树脂涂料来替代瓷砖饰面 用玻璃钢来替代不锈钢 干燥墙体系统是否可以替代石膏 -比较室内地板的不同饰面 比较有弹性的装饰面、瓷砖或者木地板 用瓷砖来替代石材 用瓷砖或者石材来替代水磨石地板 比较不同的地毯制造商 -比较不同天花板装饰 比较标准的天花板与自定义天花板 比较纤维材质的天花板与金属材质的 输送系统 -审查指定的电梯和自动扶梯 是否已经比较不同的制造商? 室内电梯