fj小净距隧道施工组织方案.doc

上传人:sccc 文档编号:4800338 上传时间:2023-05-15 格式:DOC 页数:85 大小:1MB
返回 下载 相关 举报
fj小净距隧道施工组织方案.doc_第1页
第1页 / 共85页
fj小净距隧道施工组织方案.doc_第2页
第2页 / 共85页
fj小净距隧道施工组织方案.doc_第3页
第3页 / 共85页
fj小净距隧道施工组织方案.doc_第4页
第4页 / 共85页
fj小净距隧道施工组织方案.doc_第5页
第5页 / 共85页
点击查看更多>>
资源描述

《fj小净距隧道施工组织方案.doc》由会员分享,可在线阅读,更多相关《fj小净距隧道施工组织方案.doc(85页珍藏版)》请在三一办公上搜索。

1、Gay is now a provincial key construction project of aluminum Ltd-province with an annual output of 50,000 tons of technical innovation project of environmental protection and energy saving of electrolytic aluminum project manager. In this technological transformation projects, he has overall respons

2、ibility for the day-to-day affairs of the project. In order to ensure that southern companys control the scale of investment, strengthen field management, pay special attention to project progress, and ensure a successful operation, the overall goal. He and Engineering Department under the leadershi

3、p of all the staff in the companys technical command, on the difficulties and to overcome technical difficulties in the process, work hard, have made outstanding achievements, mainly reflected in the following aspects: first, careful organization and management achieved remarkable results. Technical

4、 innovation project of the year, started and completed a series of bids and completed to date, from production engineering to put into production after nearly a year, has achieved very significant results. A project first 56 slots from dismantling the old slot just 168 days, civil engineering, insta

5、llation, commissioning, guarantee engineering quality under the premise, on the production side transformation under difficult conditions, created the national industrys fastest speeds. II 32 large prebaked electrolytic cell on November 7 has been installed, marks has an annual production capacity o

6、f 50,000 tons of electrolytic aluminum production capacity of aluminum. Entire project almost 8 months earlier than planned, achieved the goal of production transformation benefits that year, created favorable conditions for aluminum through South. Second, effectively control the investment. Project

7、 is subject to a scientific approach to bidding, bidding to make savings of 20 million Yuan, in the implementation process of the project, every domestic prices of steel, cement and other building materials, the old buildings on the base encountered great difficulties in dealing with significant inc

8、rease in the volume of civil engineering, but through rationalization and optimization, project control in fixed investment of 350 million Yuan. Third, environmental energy-saving effect of the project. Project investment of nearly 30 million Yuan, using large prebake technology and aluminum oxide d

9、ense phase and hyper dense phase conveying technology, fluoride and other harmful gases purification efficiency of up to 98%. Compared with Soderberg cell before the modification, power consumption can be reduced by 1500 tons of electrolytic aluminum, and project environmental protection and energy

10、saving effect is obvious. Four are in a relatively short period of time to the normal production. After four months of efforts, a project has put into operation all the 54 240KA large cell into regular production, stable current channel conditions and all the economic indicators are good, current ef

11、ficiency in October had reached 93%, is close to and reach the domestic advanced level. In the case of production half of the cell, this effect can be achieved and better level in the industry. 50,000 tons of electrolytic modification process, from preliminary study to equipment selection, cost cont

12、rol, project progress, quality control and coordination among the various sub-projects and various professional, technical command under the correct leadership, both from an overall perspective, emphasis on integrity, and earnestly implement the relevant laws and regulations, strictly act according

13、to the contract. He tried to learn relevant knowledge, good style of business, operational and organizational coordination ability, project efficiency, quality and safety assurance system in place, with all units involved with the coordination and good .目录一、工程概况及编制原则1、工程概况1、编制依据及原则1 1、编制依据1 2、编制原则1二

14、、施工组织及投入3、施工组织3、主要施工劳动力投入3、主要管理人员岗位职责4、施工机械设备投入6、前期施工资金安排7三、施工时间安排7、施工前期准备时间安排7、洞口施工时间安排7、洞身开挖时间7、衬砌时间安排8四、主要工程项目施工方案、施工方法8、总体施工方案8、隧道工程主要工序施工方案10、隧道工程施工方法13五、不良地质地段的施工预案与技术保证措施及小净距 隧道施工要点39、不良地质段的施工方案与技术保证措施39、小净距隧道施工要点42六、保证工程质量的措施44、保证工程质量的技术措施44、保证工程质量的经济措施48七、安全保证措施49、安全保证的技术措施49、安全保证的经济措施62八、环

15、保、水环境保护措施63、隧道排水63、便道、便桥63、弃渣场防护64、固体废弃物的处理64、大气环境及粉尘的防治措施64、降低噪音的措施65、植被保护及复耕绿化65、其它66九、文明施工措施66十、其他应说明的事项68、雨季施工措施68、与当地居民和睦相处的措施69、治安保护措施69、防洪防汛安全措施70Four outstanding works. They are derived from their own inner feelings. I also sent a student to attend the class Department speech contest, failed

16、 to get a good result, but also actively cooperate with the Department and class activities! in order to create a demonstration dorm room, our weekly class to every bedroom check, where proposed is insufficient. In order to clean up the bedroom, we use the brush brushes a bedroom again. For the clas

17、s out of a force. In the event we, many projects did not get the desired results. But we understand that we tried, and in the struggle. Also has made good progress in many of the! in my class the work carried out and the results achieved, thanks to the concern and support of the Department, thanks t

18、o instructor teachers good, proper guidance, thanks to 46 students in the class will work closely together, to work together. Of course, we also have our weaknesses, needs to be further correction in their future learning and life, with a view to achieving greater results. Five declarations of good

19、party branch branch is a fortress, a party member is a banner. Fighting in the railway engineering construction Group Headquarters Headquarters branches, a total of members 18. Role of the Xiang-GUI railway and tight South Lebanon railway, heavy, poor conditions of disadvantage, the branch closely a

20、round the construction work. Holding high the flag of our party members, unite and lead staff on the difficulties, overcome difficulties, take the zhengyou, a job well done and an engineering task, won the highly valued by leaders at all levels. Since October last year since the project began, Headq

21、uarters Branch is tightly around the center of its activities. Face South, climate is wet, sooner or later temperature larger, specific difficult, I branch from thought requirements all workers active motivated, do can long-term hard, dare fight of spirit prepared, while requirements all members lea

22、d, encouraged colleagues Zhijian each other help, each other learning business knowledge, overcome temporarily difficult, active into to engineering official starts of the prepared work in the to, play out has as a branch of fighting fortress role and members of pioneer model role. Since its start,

23、I command under the correct leadership of the party branch in the Group and the superior party, centering on building a qualified party branches, branch of the forts and the battle to play the exemplary vanguard role of party members, actively working. In command personnel less, and task heavy of si

24、tuation Xia, all members always according to party stronger, and style to are, and service better, and efficiency to high of requirements, from overall starting, better to completed has production organization, and coordination, and guarantees and the management work, in engineering progress, and qu

25、ality, and benefits, and safety, aspects are made has good of results, get has owners and the Group and grass-roots units of praise. First, give full play to the exemplary role of party members. The exemplary role of party members and cadres are silent on the command, the exemplary role of party mem

26、bers and cadres are the best of the ideological and political education. We pay close attention to party building, requires political party members and cadres must take the lead in learning, set strict demands on themselves, .81表3 马宅山隧道施工组织设计方案一、工程概况及编制原则 、工程概况长乐市滨江路岐洋段马宅山隧道东线隧道长度为563m,起讫桩号为DK0+367.

27、5+930.5,西线长度为554m,起讫桩号为CK0+360+914,隧道为上下行分离式双向六车道,该项目设计时速为50Km/h,隧道单洞建筑限界高度为5.0m,净宽为14.75m。隧道穿越主要围岩级别为、级三种围岩,各级围岩所占隧道比例如下表:围岩级别 级 级级长度(m)/百分比(%)东线隧道(563m)140m/24.87%240m/42.63%183m/32.50%西线隧道(554m)314/56.68%240/43.32%、编制原则及依据1.编制依据国家、交通部和地方政府的有关政策、法规和条例、规定;国家、交通部颁布的现行相关设计规范,施工技术规范,各种试验(检验)、检测标准(规程);

28、公路隧道施工技术规范;现行市政施工、材料、机具设备定额;现场施工调查有关资料;2. 编制原则本施组的编制将以满足招标文件的各项要求为目标,在仔细研究、深刻理解马宅山隧道的设计意图和工程本身所特有的工程特点、重点和难点的基础上,遵循下列原则进行施工组织设计的编制:质量保证原则进行施工全过程的质量控制和管理。建立健全质量管理机构和管理体制,建立“横向到边,纵向到底,控制有序”的质量保证体系,明确工程质量方针、目标,结合本工程的特征与实际情况采取切实可行、行之有效的工程质量保证措施,精心组织、精心施工,确保工程质量达到市优、力争省优。工期保障原则根据甲方对本工程的工期要求,运用网络计划技术,采取动态

29、管理,科学组织施工,合理配置资源,实现均衡生产,使各项分项工程施工衔接有序,使本工程的资源利用充分,以确保总体施工计划和各阶段施工计划的实现,从而确保总工期目标的实现。技术可靠性原则根据市政工程隧道工程的特点,结合以往施工经验,选择可靠性高、可操作性强的施工技术方案进行施工,确保工程安全、优质、快速地建成。经济合理性原则针对本工程的实际情况,本着可靠、经济、合理的原则,合理配备资源,制定适合本工程的施工方案,施工过程实施动态管理,从而使工程施工达到既经济又优质的目标。环保原则充分调查了解工程周边环境情况,施工紧密结合环境保护进行。施工中实施文明施工,减少废气、振动、噪声、扬尘污染,杜绝随意排放

30、污水、胡乱丢弃垃圾等对环境的污染。严格遵循有关环保和水保法规,采取有效的保护方案和保证措施,配合长乐市政府和及有关部门做好环保和水保工作,进行环境管理。建立环境管理体系和控制程序,建设“绿色工地”,实施“环保施工”。以人为本的原则建立、健全消防、安全、保卫、健康体系,以人为本,维护和保障施工人员的安全与健康。建立职业健康安全管理体系和控制程序并严格执行,保证职工的职业健康和安全。二、施工组织及投入、施工组织本项目工程若我单位中标,将按精简、高效的原则成立“马宅山隧道作业队”,作业队由现场负责人及技术负责人领导,下设财务、技术、仓库等办公室,有现场负责人对本工程负全责,现场施工设有开挖班组、支护

31、班组、衬砌班组、出渣班组、机械班组等。、主要施工劳动力投入1、管理人员投入为确保该项目顺利实施,投入主要管理人员4人,其中现场负责人1人、技术负责人1人、技术员1人、施工负责人1人;其他管理人员10人,其中仓库2人、采购2人、出纳1人、财务1人、测量工4人。2、施工班组及人员投入根据本工程的实际情况,现场将采取动态管理,科学组织施工,合理配置资源,实现均衡生产,使各工序施工衔接有序,使本工程的资源利用充分,达到流水作业的要求,我们将投入开挖班组2个约48人,支护班组2个约66人,衬砌班组2个约30人,出渣班组2个约10人,机械班组2个约8人、主要管理人员岗位职责1、现场负责人岗位职责 宣传国家

32、、交通运输部、地方政府的法律法规及上级单位的各项规章制度并抓好落实工作;负责现场的全面管理工作。在项目部的领导下,精心组织、统筹安排施工现场生产,认真落实项目部下达的施工任务;负责贯彻上级单位安全管理规定、落实安全施工保障措施,组织和知道作业人员安全施工,配合项目部安全专职人员做好本作业队的安全技术交底工作;负责承建工程施工安全、质量、进度和文明施工,按照项目部施工组织设计、作业指导书、技术交底等技术性文件规定和相关要求,组织本作业队人员认真学习和严格执行;负责本作业队劳务人员、机械设备施工管理和费用核算;完成项目部领导交办的其他工作。2、技术负责人岗位职责认真贯彻执行国家、交通运输部各项施工

33、规范、验收标准,认真执行建设单位和项目部各项有关规定;协助现场负责人抓好工程安全、质量、进度、文明施工等各项工作;负责本作业队的技术管理工作,参加项目部图纸会审、参与实施性施工组织设计和施工方案的制定;负责向施工负责人、工班长进行工程质量、施工安全、环保等书面技术交底,并将技术交底分类存档。指导工班组按设计图纸、施工规范等要求进行施工;检查、监督、纠正施工存在的质量、安全、工序、工艺方面的问题;参加工程质量、安全事故的调查分析;完成项目部技术部门及现场负责人交办的其他工作3、技术员岗位职责认真贯彻执行国家、交通运输部各项施工规范、验收标准,认真执行现场负责人、技术负责人各项有关规定;协助技术负

34、责人做好技术交底工作;跟班作业,纠正施工中安全、质量、环保、工序、工艺、文明施工等方面存在的问题,发现重大安全、质量隐患立即停止并报告上级;做好施工原始资料等相关技术资料的编写、收集整理;参加工程质量事故调查分析;做好对隐蔽工程的关键部位、重点工序的施工过程进行旁站监督和指导;完成现场负责人和技术负责人交办的其他工作。4、现场施工负责人岗位职责全面负责工点施工生产的现场组织和指挥工作;严格执行班前交底制度,合理安排和组织工班作业,提高劳务作业工作效率和机械施工效率,节约施工成本;组织班组完成作业队下达的施工任务;负责记录进出隧道人员台账;负责工班施工的质量、安全、进度、环保和文明施工管理;协助

35、现场负责人进行劳务人员和施工机械的管理;完成现场负责人交办的其他工作。、主要施工机械设备投入见下表投入本合同工程的主要施工机械机械名称规格型号额定功率(kw)或容量(m3)或吨位(t)厂牌及出厂时间数量新旧程度(%)小计其中拥有新购租赁挖掘机PC22021190%装载机ZL50C3390%自卸运输车1520T66100%混凝土拌合站HZS752290%混凝土搅拌运输车8m32290%发电机组400kw11100%湿喷机30m3/h44100%空压机L-20/2.520m344100%空压机L-10/810m322100%锚杆专用 注浆泵130L/min2295%开挖台车22100%凿岩机D80

36、505095%液压式衬砌台车长12m,厚10mm2290%砼输送泵HBT60E2290%、前期施工资金安排三、施工时间安排本工程施工的计划总工期为10个月,计划2013年12月25日开工,2014年10月24日竣工,该工期为正常日历天数,具体时间安排如下:、施工前期准备工作时间安排如下:人员进场时间:2013年12月16日2013年12月23日,截止12月23日,人员全部进场。机械设备进场时间:2013年12月18日2013年12月26日,截止12月26日机械设备全部到位。混凝土搅拌站建站时间:2014.1.102014.2.10、洞口施工安排时间如下:洞口开挖时间:东线2013年12月192

37、014年1月14 西线2013年12月222014年1月11日2.套拱、管棚施工时间:东线:2014年1月15日2014年1月23日(两台钻机施工)、洞身开挖时间:具体见隧道工序循环时间及完成时间表隧道工序循环时间表围岩级别工序名称时间 (小时)循环进尺时间 (小时)循环进尺 (m)月进尺 (m)东线完成时间(月)西线完成时间(月)级打钻319.7136.5 3.83装药、放炮0.7通风0.5出碴3初期支护12.5级打钻3.522.82.578.9 3.043.98装药、放炮0.8通风0.5出碴3.5初期支护14.5级打钻5.517.23.2134.0 1.371.79装药、放炮1.2通风0.

38、5出碴3.5初期支护6.5贯通所需时间(月)8.245.77、隧道洞身衬砌、支护及其他分项工程时间见工期计划与施工进度安排表时间安排说明:1.为确保先行洞超前40m左右,在实际施工时,时间可以适当调整;2.西线隧道先贯通,贯通后西线隧道内的施工班组及模板和机械设备可以根据东线隧道内的实际需要将其调入,以加快施工效率,提高施工进度。四、主要工程项目的施工方案、施工方法总体施工方案根据设计文件、现场考察和我公司的现有机械设备与施工经验,确定的总体施工方案为:短隧道独头掘进,左右两洞同时进行,洞口先后错开40 m。隧道软弱围岩段采用风镐和人工、长臂挖掘机开挖;围岩强度和整体性允许的地段,采用风动凿岩

39、机钻眼,光面爆破采用非电塑料导爆管起爆系统,毫秒微差有序起爆。出碴采用挖掘机、侧卸式装载机配合运输汽车无轨方式出碴。初期支护的喷砼采用CP-5B型湿喷机。防水层施工采用移支或作业台架、无钉铺设双焊工艺。二次衬砌采用12 m长的液压衬砌台车,搅拌输送车运送砼,输送泵泵送灌筑工艺。正洞各类围岩施工方案如下:级围岩地段:级围岩采用半断面正台阶法施工。先打入超前砂浆锚杆,进行上弧导坑开挖和架立钢支撑、拱部锚喷支护,再进行下部开挖和支护,最后浇注二衬砼。根据设计地质资料和设计要求进行开挖,同时将实际情况与设计进行比对,并对各项参数做适当调整。开挖支护顺序见图1,施工工艺流程详见框图2。级围岩地段:级围岩

40、地段采用三台阶法施工,具体施工方法见“三台阶工序示意图”。先开挖支护部, 并施做超前支护,部与部左右侧交错开挖,一台阶与二台阶长度控制在510m左右,当、部开挖一定长度后,开挖中槽部,然后交错开挖、部,同时控制二台阶与三台阶的长度控制在510m左右,当、部开挖一定距离后,开挖部,最后灌注仰拱和衬砌。V级围岩地段: V级采用中隔壁法施工。先在一侧打入超前注浆小导管,开挖侧壁导坑,进行初期支护,然后进行剩余部分开挖和支护,并在拆除临时支护后及时浇注二衬砼。开挖支护顺序见图3,V级围岩具体施工工艺流程详见框图4。、隧道工程主要工序施工方案1. 隧道施工机械配套方案隧道施工机械配套是针对隧道大断面的特

41、点,以实现机械化均衡生产为目标,配套的生产能力为均衡施工能力的1.2以上。施工中的关键机械,如混凝土的拌和设备、运输设备、混凝土喷射机、混凝土输送泵、通风机、抽水机等都有备用数量。隧道施工配置栈桥式跨越设备,来确保仰拱施工超前;衬砌结构采用边墙、拱部一体化施工的整体式衬砌台车。施工机械选用排污达标、噪音小的机械,动力选择电力机械。开挖作业机械配套示意图、初期支护机械配套示意图、防水板及二次衬砌机械配套示意图如下图所示2. 洞口段施工方案先施做洞顶截水沟,清除危石。边、仰坡及明洞土石方分层开挖,随挖随喷锚支护,尽量减少植被的破坏。开挖至暗洞的上半断面底标高后,施做管棚加做套拱形成支点再进暗洞。3

42、 洞身施工方案超前综合地质预报方案隧道超前地质预报,就是根据设计的地质勘测资料,对不良地质段进行补充地质探查,进一步了解和掌握隧道通过区的水文地质条件,对水源及其通道作出初步判断,以便根据不同的地质情况选用不同的施工方法,确保施工安全。施工时在正洞工作面按照“由远至近,逐步加密”的综合地质预测方法,根据设计文件,先用物探手段探测掌子面前方及坑道周围的地质异常体,特殊地段用水平钻孔法进行验证,对开挖面前方及周围的地质情况进行准确预报,确定施工方案。洞身开挖及出碴施工方案洞身级围岩采用半断面正台阶法,循环进尺3m,级围岩采用三台阶法、级围岩采用CRD法,循环进尺2.0m;级围岩循环进尺为不大于二榀

43、拱架间距。采用铲装机(或装载机)配合22.5t自卸汽车出碴。 初期支护施工方案初期支护紧跟掌子面,喷射混凝土采用ZSP-型湿喷机喷射作业台架;锚杆利用打钻台架,采用风钻打眼,人工安设;型钢钢架(钢筋网)在洞外分段(分片)加工、校正,运进洞组装架(挂)设。喷料在洞外自动计量拌合站拌和,混凝土搅拌运输车送料。防排水施工方案采用三大技术:无钉铺挂技术、热风双面焊缝技术及分区防水技术。防水板加无纺布采用无钉铺设,板材在洞外裁板加工,洞内利用多功能平台配合人工进行防水层的挂设作业。防水板接头采用热焊法整合。焊接完后对焊缝进行充气检查。主洞防水板设于拱部及边墙,要求与施工缝、沉降缝设置的背贴式止水带、钢板止水带,以及排水PVC管配合使用,形成防水分区,分区长度为12m。 仰拱及二次衬砌施工方案仰拱超前,采用仰拱作业栈桥,整体浇注。填充混凝土根据中心水沟的位置分左右两半幅施工,栈桥跨度为18m、桥面宽4.5m。混凝土搅拌运输车配溜槽浇注,搅拌站拌制混凝土。二衬施工配置L=12m的模板台车,拱墙整体浇注。混凝土拌合站拌制,混凝土输送车运输,泵送入模。附着式振动器配合插入式捣固棒捣固。不良地质地段施工方案施工中做到先探后挖,采用综合地质预报手段,确

展开阅读全文
相关资源
猜你喜欢
相关搜索

当前位置:首页 > 建筑/施工/环境 > 农业报告


备案号:宁ICP备20000045号-2

经营许可证:宁B2-20210002

宁公网安备 64010402000987号